DP Energy’s proposed 700MW Euston Wind Farm project in New South Wales, Australia, has progressed through important early-stage development activities since it was first announced in 2023. However, the project has yet to secure final development approval, with the NSW Planning Portal continuing to list it as being at the Prepare Environmental Impact Statement (EIS) stage.
The development has also undergone an important ownership and project-development transition. DP Energy confirms that, following the South West Renewable Energy Zone (SW REZ) access-rights tender, its Australian gentailer partner took control of the project to advance it towards construction and operation.
Euston Wind Farm Project Moves Beyond Its 2023 Development Milestone
When DP Energy announced the Euston Wind Farm in November 2023, the company had received the Secretary’s Environmental Assessment Requirements (SEARs) from the NSW Department of Planning and Environment. The developer was preparing the project’s EIS.
The development was originally presented as a nominally 700MW onshore wind farm located approximately 8km north of Euston. This is within the Balranald Shire Local Government Area.
Since then, the project has progressed through additional environmental investigations, land agreements, community engagement and grid-access planning.
One particularly important development was DP Energy’s completion of two years of Bird and Bat Utilization Surveys. These investigations, together with project consultation with local First Nations communities, formed part of the work undertaken to reduce environmental impacts. It also prepared the project for subsequent assessment.
DP Energy also secured land agreements covering both the proposed wind farm site and its grid connection route.
The company completed the initial project scoping work. DP Energy then obtained the environmental assessment requirements needed to prepare the development application.
However, despite this progress, the project is not yet construction-ready. The NSW Planning Portal still lists the development as preparing its EIS, indicating that the environmental assessment and statutory planning process remain outstanding.

DP Energy Hands Over Euston Wind Farm Following Grid Access Rights Tender
One of the most significant developments since the original 2023 announcement is the change in project control.
According to DP Energy, the company partnered with a major Australian electricity generator and retailer (gentailer) to participate in the South West Renewable Energy Zone access-rights tender.
The partnership sought access to Project EnergyConnect. EnergyConnect is the major transmission interconnector being developed by Transgrid to strengthen electricity transfers between New South Wales and South Australia.
Following the conclusion of the access-rights tender, DP Energy confirmed that its gentailer partner had taken control of the Euston Wind Farm project.
The arrangement also represents a transition from early-stage project development to the next phase of project delivery. The new controlling partner is also expected to advance the development towards construction and operation.
Importantly, DP Energy has not publicly identified the gentailer partner.
Project Scope Revised to 96 Wind Turbines and 500MW Battery Storage
The latest project details on the proposed Euston Wind Farm has significantly changed since the 100 turbines initially announced in 2023.
The Euston Wind Farm is now described in the NSW planning documentation as a development comprising up to 96 wind turbines, battery storage and associated infrastructure.
It features the following project specifications:
- Up to 96 wind turbines, each with a nominal capacity of 7.2MW.
- Maximum turbine tip height of approximately 275 meters.
- Total proposed wind generation capacity of 700MW.
- A 500MW/2,000MWh battery energy storage system (BESS).
- On-site electrical infrastructure operating at 33kV and 220kV, with provision for a 330kV connection.
- A 18-kilometre overhead or underground export connection.
- A grid connection and switching yard.
- Internal access roads, substations, electrical cabling and supporting facilities.
Additionally, the battery component is particularly important. This is because it would allow electricity generated during periods of strong wind production to be stored and dispatched when required.
The combination of wind generation and four-hour battery storage would also provide additional flexibility in managing electricity supply and demand.
The final turbine selection, engineering design and construction configuration remain subject to further development and regulatory assessment.
Euston Wind Farm Environmental Assessment and Planning Approval Remain Outstanding
Another important development since earlier 2023 planning is the progression of the project’s environmental assessment requirements.
The NSW Government issued updated Secretary’s Environmental Assessment Requirements in May 2025. This followed changes to the state’s Renewable Energy Planning Framework introduced in late 2024.
Euston Wind Farm project is being assessed as a State Significant Development under application number SSD-62466963.
It is also a controlled action under Australia’s Environment Protection and Biodiversity Conservation Act 1999 (EPBC Act). Federal environmental assessment is also to be undertaken through the relevant bilateral or accredited assessment process.

Furthermore, the environmental assessment is particularly important because of the project’s proposed location near environmentally significant landscapes, including the Willandra Lakes Region.
The federal referral documentation identifies potential impacts associated with vegetation clearing, turbine construction, access tracks.
DP Energy also previously reported undertaking two years of bird and bat utilization surveys. This was alongside community consultation and project optimization to minimize environmental impacts.
As of November 2026, however, the NSW Planning Portal still identifies the Euston Wind Farm project as being at the Prepare EIS stage. It has not progressed to public exhibition, submissions assessment or final determination.
This means that the wind farm has not yet received the necessary state development consent to commence construction.
South West REZ Grid Connection Presents a Major Development Challenge
Perhaps the most consequential issue for the Euston Wind Farm project is access to transmission infrastructure.
The project was initially developed around the opportunity to connect to the South West Renewable Energy Zone and Project EnergyConnect, the transmission interconnector linking New South Wales and South Australia.
DP Energy also confirmed that it partnered with an Australian gentailer to participate in the South West REZ access-rights tender. Following the tender process, the partner took control of the project.
However, the subsequent access-rights allocations present a significant complication.
On April 23, 2025, the NSW Government announced four successful projects with a combined allocated capacity of 3.56GW:
- Origin Energy’s Yanco Delta Wind Farm – 1,460MW.
- Spark Renewables’ Dinawan Energy Hub – 1,007MW across its three connection allocations.
- Someva and AGL’s Pottinger Energy Park – 831.2MW.
- BayWa R.E.’s Bullawah Wind Farm – 262.3MW.
Euston Wind Farm project was not included among the successful access-rights projects.
More importantly, EnergyCo’s draft South West REZ Headroom Assessment, published in 2026, found that there was no additional headroom available for further access rights based on the existing network and allocations.
The assessment was placed on public exhibition until November 9, 2026.
This presents a challenge for Euston Wind Farm because projects seeking to connect to the designated South West REZ access-rights network must hold an access right. This is also a potential challenge for the 1.4GW Baldon Wind Farm project in NSW that recently secured planning approval but was not in the South West REZ successful access-rights projects list.
The development could also potentially investigate alternative connection arrangements outside that network. This is, however, subject to technical feasibility, regulatory requirements and available transmission capacity. Conclusively, no confirmed alternative grid connection arrangement has been publicly established for the project.
Euston Wind Farm Construction Timeline and Investment Outlook
The project’s original development schedule anticipated construction commencing in 2025 and completion in 2027.
However, these dates were established before the project completed its environmental assessment and secured final planning approval.
With the NSW Planning Portal still listing the development at the Prepare EIS stage in November 2026, the original construction timetable is no longer a reliable indication of when work will begin.
The project developer also has not confirmed final construction budget, engineering, procurement and construction contractor, turbine supplier or financial close.
The handover to the Australian gentailer may provide the project with additional development and commercial resources. Nevertheless, its ability to advance will depend on resolving the environmental approval and grid connection requirements.
For now, the 700 MW Euston Wind Farm project in Australia remains a prospective large-scale renewable energy development.

Euston Wind Farm Project Fact Sheet
Original developer: DP Energy Australia
Alternative project company: Balranald Wind Farm
Type: Onshore wind farm and battery energy storage
Location: 7.6km north of Euston, Balranald Shire, New South Wales
Renewable energy zone: South West Renewable Energy Zone
Current project controller: Unnamed Australian electricity generator and retailer (gentailer), according to DP Energy
Wind generation capacity: 700MW
Number of turbines: Up to 96
Individual turbine capacity: 7.2MW
Maximum turbine tip height: 275 meters
Battery storage capacity: 500MW/2,000MWh
Grid infrastructure: 33kV, 220kV and 330kV infrastructure
Proposed export connection: 18km
Electricity market: National Electricity Market (NEM)
State planning application: SSD-62466963
Federal environmental referral: EPBC 2023/09695
Initial SEARs: October 2023
Updated SEARs: May 2025
Original construction target: 2025
Original completion target: 2027
Current planning status: Prepare Environmental Impact Statement
Grid access: Not included among the four initially awarded South West REZ access-rights projects
Latest development: DP Energy confirmed project handover to its unnamed Australian gentailer partner
Project Developers, Contractors and Stakeholders
DP Energy Australia – Original project developer responsible for early-stage development, land agreements, environmental investigations and community engagement.
Unnamed Australian gentailer – DP Energy’s partner that subsequently took control of the project and is expected to advance its development.
Balranald Wind Farm Pty Ltd – Project special-purpose vehicle identified in Infrastructure Pipeline’s procurement information.
EnergyCo NSW – Responsible for coordinating the South West Renewable Energy Zone and associated transmission infrastructure.
Transgrid – Transmission network stakeholder associated with Project EnergyConnect and the regional electricity transmission network.
NSW Department of Planning, Housing and Infrastructure – State planning and environmental assessment authority.
Australian Department of Climate Change, Energy, the Environment and Water (DCCEEW) – Federal environmental assessment stakeholder.
Balranald Shire Council – Local government authority for the project area.
Australian Energy Market Operator (AEMO) – National electricity market and power system stakeholder.

DP Energy Announces 700MW Euston Wind Farm Project in Australia
Reported November 8, 2023 – DP Energy‘s ambitious Australian Wind Farm Project is making waves Down Under. The Cork-based company is charging ahead, having recently achieved a significant milestone in its pursuit of approval for this massive venture. The Irish renewable energy powerhouse is now one step closer to realizing its vision of a 700MW wind farm in New South Wales, Australia.
In a recent announcement, DP Energy revealed that it successfully secured the Secretary’s Environment Assessment Requirements (SEARs), signifying a pivotal juncture in the project’s journey. With SEARs secured, they now prepare for the crucial step of crafting an Environmental Impact Statement (EIS) to obtain approval.
The selected site, situated 8km north of Euston in New South Wales, will accommodate 100 turbines, harnessing wind power for the national grid. Furthermore, the proposal encompasses infrastructure elements such as roads, cabling, a battery energy storage system, and maintenance facilities.
Also Read: Riverina Battery System Powers Australia with 150 MW/300 MWh Capacity
DP Energy’s Vision: Powering Australia with 700MW Wind Farm Project
When operational, DP Energy’s extensive wind farm will supply electricity to approximately 325,000 homes in New South Wales. Hugh Cantwell, Head of Projects for DP Energy Australia, enthusiastically hailed the acquisition of SEARs as a “pivotal milestone” for this transformative undertaking.
Cantwell’s excitement stems from the Australian wind farm project’s alignment with the government’s goals. This collaboration paves the way for an affordable, clean, and dependable electricity system in New South Wales. It underscores a significant step towards the region’s green energy evolution.
DP Energy’s track record is nothing short of impressive. Last month, the company received approval to start constructing the 430MW Callide Wind Farm project in Australia. The project will commence next year and will take an estimated two years to complete.
DP Energy’s global presence spans across Australia, Canada, Ireland, and the UK. Notably, with a portfolio exceeding 1GW in renewable projects, the company is headquartered in Cork. Furthermore, they lead the renewable sector, boasting a project pipeline exceeding 9GW, which covers onshore wind, solar, and offshore wind technologies.
In a strategic move, DP Energy recently joined forces with offshore sector supplier SBM Offshore, with a shared vision of pioneering floating offshore wind energy projects off the Canadian coast, specifically Nova Scotia. Since 2021, the company has actively engaged in Nova Scotia, diligently studying the region’s energy challenges and prospects.
In 2021, DP Energy forged partnerships with two Japanese companies, collaborating on a tidal energy project aptly named Uisce Tapa. These strategic alliances and their trailblazing projects underscore DP Energy’s commitment to reshaping the global energy landscape.
With unwavering dedication and a remarkable track record, DP Energy aims to create a significant impact in Australia and beyond. Their Australian wind farm project represents not just a milestone but a beacon of hope for a greener future.