Latest Updates on Mozambique-Malawi (MOMA) Power Interconnection Project

Home » News » Latest Updates on Mozambique-Malawi (MOMA) Power Interconnection Project

The foundation stone has been laid to officially mark the start of the implementation of the Mozambique-Malawi Mozambique-Malawi (MOMA) power interconnection project in Mozambique. The stone was laid by Filipe Nyusi, the fourth President of Mozambique and his Malawian counterpart, Lazarus Chakwera.

The 400-kilovolt transmission line that would provide Malawi with 50MW of power from Mozambique is projected to cost US$ 62M, with US$ 35M going toward the 142-kilometre line in Mozambique and the remaining funds going to the 76-kilometre line in Malawi. There will be 527 high voltage pylons in all.

A second component of the project is the US$ 21M enlargements of the Matambo substation, which will ensure the dependability of the power supply.

Importance of the Mozambique-Malawi Mozambique-Malawi (MOMA) power interconnection project

President Nyusi emphasised that the project’s development is part of the Southern African Development Community (SADC) master plan for energy infrastructure from 2018-to 2043. It will greatly contribute to strengthening Mozambique’s regional integration with neighbouring SADC nations.

According to President Nyusi, the interconnection project “opens another window of opportunity for job development and will convey the aspiration of the peoples of the two nations to have dependable, high-quality power. He went on to say that this power supply will promote new investments in industry and tourism, as well as favour mechanisation, which will enhance production. It will also make health care and education more accessible.

Chakwera said the new power line would provide a safe and dependable electrical hookup. With an initial supply of 50 megawatts, Malawi will also be able to participate fully in the Southern African Power Pool (SAPP). He also stated that Malawi is interested in increasing its power purchase from Mozambique from 50 to 110MW and bemoaned that Cyclone Gombe had recently wrecked portions of Malawi’s energy infrastructure, resulting in a loss of 129MW on the system that would take time to restore.

Reported earlier

Aug 2017

Mozambique-Malawi Mozambique-Malawi (MOMA) power interconnection line to evacuate 200MW

The Mozambique-Malawi Mozambique-Malawi (MOMA) power interconnection project is officially set to begin in 2018. This comes after two decades of signing a power trade agreement. According to the Southern Times, the delay in the project has been due to former Malawian president Bingu wa Mutharika. He had argued that Malawi was too poor to afford the monthly bill, expected to cost $480,000.
“This project will also involve the erection of a 218km high voltage power line with the capacity to transmit 200MW,” the report further explains. Mateus Magala, president of the Mozambican state power company, Electricidade de Moçambique, said he expects financing of the project to be completed within three years.
“Most of this energy will be produced by the Cahora Bassa hydroelectric dam,” he added.
Malawi allocated $18M to the energy sector in the 2017/18 fiscal year.  In Malawi’s President Peter Mutharika’s state of the nation address, he said Energy is a catalyst for socio-economic development. In this regard Malawi is implementing programmes and projects aimed at improving energy generation, transmission as well as distribution.
Mozambique-Malawi power transmission lines

Mozambique will construct 140km while 78km will be the responsibility of Malawi. The major element in the interconnection will be a 400kV transmission line between two substations. One will be at Matambo, in the western Mozambique province of Tete and the other at Phombeya in Malawi.

9% of the Malawian population has access to electricity in both urban and rural areas. For this reason, there are projects planned to improve electricity connections countrywide.

Mutharika cited the enactment of the Electricity Act of 2016 that created the Electricity Generation Company. It took over the electricity generation function from the Electricity Supply Corporation of Malawi.

“Completion of a feasibility study and environmental and social impact assessment for Malawi and Mozambique power interconnector, the commencement of the Malawi Rural Electrification Program (MAREP) Phase 8 which will connect 336 rural centres throughout Malawi to the national electricity grid and completion of feasibility studies for the 300MW Kamwamba Coal-fired Power Plant,” he said.

Aug 2019

Mozambique inks deal to complete Mozambique-Malawi (MOMA) Power Interconnection Project

The government of Mozambique through Electricidade de Moçambique (EDM) has secured a deal with German Development Bank (KFW) to finance the completion of the Mozambique-Malawi Interconnection Project.

The Ministry of Mineral Resources and Energy in Mozambique confirmed the development adding that the project involves the construction of a 440KV substation and a 218km power transmission line between Matambo (Tete province) and Phombeya (Malawi), connecting the electricity networks of the two countries.

Also Read: Mozambique inaugurates 40MW Mocuba solar power plant

Mozambique-Malawi Interconnection Project

Mozambique’s share of the credit is US $45m and involves the installation of a 135km, 220KV power line while on the Malawi side, about 75 km of the 220-kilovolt transmission line will be built and a new 220KV substation installed at Phombeya.

The project will also connect Malawi to the Southern African Power Pool (SAPP) for the first time, allowing two-way energy trade between the two countries. This will ensure a much-needed diversification in Malawi’s electricity supply and allow the export of any off-peak power surpluses and also provide Mozambique’s energy sector with a new revenue source. The SAPP oversees electricity trade among member countries in southern Africa

“Mozambique is rich in conventional and renewable sources of energy and presents itself as a regional energy hub, so the interconnection between Mozambique and Malawi provides access to the regional market, enabling large energy projects in Mozambique to become viable,” said Mozambique’s Minister of Mineral Resources and Energy, Max Tonela.

“Malawi will thus be able to participate equally with all other Member States in regional electricity trade, including importation and exportation to the regional market. In fact, it is another important step towards regional integration in the context of the Southern African Development Community,” he added.

Nov 2021

Construction of the Mozambique-Malawi (MOMA) Power Interconnection line in Malawi Begins

On Tuesday, November 23, President Filipe Jacinto Nyusi, who arrived in the country on Monday, joined his host counterpart President Lazarus Chakwera at Phombeya in Balaka District to kick off construction on the Mozambique-Malawi power transmission link project in malawi.

The interconnection project comprises the building of a 400KV Matambo substation in Tete, Mozambique, and 218km of transmission lines from that source into Malawi, from which Malawi is scheduled to receive 50 megawatts of power. The transmission lines will run 142 kilometres from Matambo substation to Phombeya, Malawi, passing through Mwanza and Neno districts, and will be finished in 2023.

The completion of this project will result in enhanced access to power in Malawi, with an initial capacity of 50MW and the ability to expand in the future. Malawi’s existing power-producing capacity is now hovering around 50MW, according to the 2017 Integrated Resource Plan.

By 2030, peak energy demand is expected to reach 1,860MW. The interconnection project aims to contribute to regional economic growth by linking Malawi’s electricity market with the Southern African Power Pool (SAPP) to balance the region’s power deficit through regional power trading.

Phase 1 Of the Mozambique-Malawi Power Transmission

The Mozambique-Malawi power transmission link project’s first phase includes a technical and economic feasibility study, project definition and scope, and an environmental and social impact assessment, all of which were completed in 2017.

President Chakwera mentioned the railway repair project that the two nations are working on to connect Malawi to the Sena Line that runs from Vila Nova de Fronteira to Marka across the border. He went on to say that this connectivity project is another milestone in the two countries’ relationship.

According to Chakwere, the initiative intends to open up trade channels in the SAPP, with the possibility of future trade and power exchanges. With the completion of the Malawi-Mozambique Interconnector, he stated that progress toward adding 1,000 megawatts to the national grid over the next four years is being made.

The World Bank’s IDA Credit is worth $15 million, the European Union’s KFW Grant is worth $20 million, and the Malawi government is worth $3.5 million. It is planned to generate over 1000 jobs throughout its construction. Nyusi expressed his delight at the Malawi government’s investment of US$3.5 million in the project for the installation of transmission lines along the 76-kilometre stretch, claiming that this shows Chakwera’s administration’s dedication to the project.

Mozambique-Malawi (MOMA) Power Interconnection Project now Underway

The Electricity Supply Corporation of Malawi (ESCOM) has awarded key contracts for the construction of the 218-kilometre Malawi-Mozambique Interconnector Project and Matambo Substation as part of the Mozambique-Malawi Interconnection Project (MOMA).

ESCOM Senior Project Manager Alex Kaitane gave a news conference in Blantyre on Tuesday to update the public on the MOMA Project’s progress.

Also Read: Solar Power Plant IPPs fail to take off in Zimbabwe

According to him, the transmission line and expansion of Phombeya will be built by L&T India, while the Matambo Substation Upgrade will be built by Sino Hydro of China, with both projects being managed by Gopa Intec International of Germany.

Completion date for Malawi-Mozambique Interconnector Project

Kaitane said that the project would now be completed in October 2023 rather than December 2022 as scheduled due to Covid-19, which delayed work and organization.

He went on to note that the arrival of Covid-19, which happened while we were already doing some preparatory work for the project, disrupted our work and organization, and was the major reason for the delays.

The Joint Project Implementation Unit, which is made up of staff from EDM in Mozambique and ESCOM in Malawi, administers and implements the Malawi-Mozambique Interconnector Project.

Kaitane said they had pushed contractors and consultants to make the most of the local labour, which will always be accessible if Covid-19 strikes. They are unable to mobilise into the country to meet the completion date.

Senior Project Accountant Joseph Kamwendo refuted fears that the Kwacha’s fluctuation would affect the project’s worth, claiming that the funding was done in US dollars and Euros at the outset.

He went on to claim that the majority of the contracts were given to foreign contractors who would be paid in dollars and that all of their quoting was done in dollars as well, so the Kwacha volatility would have no effect.

The MOMA initiative is supported by the World Bank, the European Union through KfW, and the Malawian government through ESCOM. It will cost you a total of USD127 million. Once completed, it will provide 50 Megawatts to the country’s electrical grid.

https://constructionreviewonline.com/news/mozambique-inks-deal-to-complete-mozambique-malawi-interconnection-project/#:~:text=Mozambique%20inks%20deal%20to%20complete%20Mozambique%2DMalawi%20Interconnection%20Project,-Modified%20date%3A%20Aug&text=The%20government%20of%20Mozambique%20through,the%20Mozambique%2DMalawi%20Interconnection%20Project.

https://constructionreviewonline.com/news/mozambique-malawi-power-transmission-line-evacuate-200mw/

https://constructionreviewonline.com/news/malawi-mozambique-interconnector-project-now-underway/

https://constructionreviewonline.com/news/construction-of-the-mozambique-malawi-power-transmission-link-begins/