240 MW Stor-Skälsjön onshore wind farm in Sweden to start operations after delay, producing 800 GWh annually

Home » Energy » Wind power » 240 MW Stor-Skälsjön onshore wind farm in Sweden to start operations after delay, producing 800 GWh annually

Stor-Skälsjön wind farm in Sundsvall and Timrå municipalities in northern Sweden has announced completion through developers Eolus and Hydro Rein. The 240 MW onshore wind farm will produce around 800 GWh of renewable energy annually from its 42, 200-meter tall, Siemens Gamesa wind turbines.

Project factsheet

Location: Near Slättmon in Sundsvall and Timrå, Northern Sweden

Owner: Hydro Rein and MEAG

Developer: Eolus-Hydro Rein JV

Asset manager: MEAG

Asset management services by: Eolus as per a 15-year contract

Wind farm type: Onshore

Annual production: 800 GWh

Production capacity: 240 MW

Turbine units: 42

Turbine height: 200 meters

Rotor diameter: 170 meters

Contractor: Siemens Gamesa for wind turbines

Start of construction: 2022

Contractor: Svevia for construction activities

Wind turbine installation date: 2023

Completion of construction: 2025

Project commissioning date: 2025

Eolus and Hydro Rein’s Stor-Skälsjön wind farm project in Sweden

Located in Sundsvall and Timrå municipalities in northern Sweden, plans were to have the wind turbine supply Telenor. The telecom infrastructure provider signed a 10-year Power Purchase Agreement with Hydro Energi.  This is according to Hydro Rein, a leading provider of renewable energy to industrials.

240 MW Stor-Skälsjön onshore wind farm in Sweden to start operations 2025
Installation of a Siemens Gamesa wind turbine at the 240 MW Stor-Skälsjön onshore wind farm in Sweden that will soon start operations

To join the ranks of other wind energy projects across Europe in supplying the electricity grid, Eolus and Hydro Rein’s Stor-Skälsjön wind farm in Sweden will also address the needs of the locals.

Also read: Profen 2 wind farm project in Germany progress with Vestas 62 MW turbine supply

Alongside the awarding of community grants to the locals since last year, an estimate of 160,000 homes in the northern Sweden location will also benefit from the farm’s renewable energy generation. Regarding the grants, a local school and community center have so far been among the inaugural recipients. According to Eolus, these will be distributed annually for the entire lifespan of the wind farm.

Also read: Siemens Gamesa Signs Agreement for Establishing 500MW Gulf of Suez Wind Power Project

The 2024 to 2025 construction completion delay

According to official sources in Eolus, after construction activities broke-ground in 2022, and Svevia got to the digging, hauling, and all entails of construction, technical issues arose. These have so far been tied to a supplier. This is what brought about the delay and pushed the completion and commissioning date for Eolus and Hydro Rein’s Stor-Skälsjön wind farm from 2024 to 2025.

240 MW Stor-Skälsjön onshore wind farm in Sweden to start operations 2025 after 2024 delay

Svevia also handled the installation of crane sites, foundations, roads, and power grids for the renewable wind energy project in Sweden.

Back to business on the Stor-Skälsjön wind farm

Expressing the delight of a greener future for the project and companies involved, the CEO of Eolus said the following in an official statement. “We are pleased that the project has now reached completion, and we look forward to continuing our collaboration with Hydro Rein and MEAG”. A collaboration that will majorly feature, “[…] under the asset management agreement for the facility”, said Per Witalisson in official statement. Witalisson is the CEO of Eolus.