Home » First Five Turbines Installed at the 1.2 GW Baltic Power Offshore Wind Farm

First Five Turbines Installed at the 1.2 GW Baltic Power Offshore Wind Farm

Home » First Five Turbines Installed at the 1.2 GW Baltic Power Offshore Wind Farm

Baltic Power, a pioneering joint venture between Orlen and Northland Power, has marked a significant achievement in its 1.2 GW offshore wind farm project. Nearly half of the monopiles and transition pieces have now been installed in the Polish Baltic Sea. In addition, monopiles, the robust steel foundations for turbines, are being positioned by Van Oord’s heavy-lift vessel, Svanen, with monopiles supplied by Steelwind Nordenham and transition pieces (TPs) from Smulders. Earlier this spring, five TPs were successfully installed, making history as the first ever in Polish Baltic waters and demonstrating substantial progress toward the project’s ambitious goals.

Progress Below and Above the Waves

The next phases of work will focus on subsea infrastructure, starting with inter-array and export cable installation. This will be followed by the autumn installation of steel pylons for offshore substations, meticulously assembled at shipyards in Gdynia and Gdańsk. Key components such as turbine nacelles, subsea cables, and substation foundations are being produced in several Polish cities. These include Szczecin, Bydgoszcz, the Tri-City area, Żary, and Niemodlin. This widespread production footprinthighlights Baltic Power’s strong commitment to domestic industry involvement and local economic impact.

Also Read Poland to construct its longest single transport tunnel of any kind

Onshore Facilities and Grid Integration

Baltic Power’s progress is not limited to offshore activities. In May, the company opened its state-of-the-art operations and maintenance (O&M) base in Łeba. This facility will operate as the Marine Coordination Centre, managing the wind farm’s operations for the next three decades. Onshore construction in Choczewo is also advancing, with a new substation under development to connect the offshore wind farm to Poland’s national grid. Furthermore, this integrated approach ensures that offshore generation will be efficiently transmitted to meet national electricity needs.

Also Read Estonia Leads Rail Baltica Rollout with $1Bn Infrastructure Deal

Looking to the Future

Set for commissioning in 2026, the Baltic Power offshore wind farm will supply renewable energy to approximately 1.5 million Polish households, meeting about 3% of the country’s electricity demand. Orlen is already preparing for the next chapter, with plans for additional offshore wind projects totaling 5.5 GW of capacity. In addition, this includes the upcoming Baltic East project slated for Poland’s December auction. Notably, the Svanen vessel used in monopile installation was recently upgraded, extending its gantry crane by 25 meters and boosting its lifting capacity to 4,500 tonnes. Further, this makes it one of the most advanced installation vessels globally, ideally positioned for current and future offshore wind developments.

Project Overview

Joint venture between Orlen and Northland Power.

1.2 GW capacity offshore wind farm in the Polish Baltic Sea.

Nearly 50% of monopiles and transition pieces installed.

Van Oord’s Svanen vessel used for monopile installation.

First-ever transition pieces in Polish Baltic waters.

Subsea cables and offshore substation pylons set for installation next.

Domestic production in cities like Szczecin, Gdynia, and Bydgoszcz.

O&M base in Łeba opened in May 2025.

Commissioning in 2026, powering 1.5 million homes (~3% of Poland’s demand).

Future expansion planned to 5.5 GW, including Baltic East project.

Also Read Vestas to establish offshore wind blade factory in Poland

Leave a Comment