The Mega $2 Billion Julius Nyerere Hydropower Project Nears Completion as its Fifth Turbine Goes Live

Home ยป News ยป The Mega $2 Billion Julius Nyerere Hydropower Project Nears Completion as its Fifth Turbine Goes Live

Recent insights highlight that the Julius Nyerere Hydropower project is nearing completion. This is as the government of Tanzania readies itself to activate the projectโ€™s fifth turbine. Once operational, Tanzaniaโ€™s electricity generation is expected to ramp up significantly. Furthermore, the mover will mark a significant step towards the projectโ€™s full operational capacity. Once all nine turbines are in full gear, it is expected to generate 2,115 megawatts of electricity. The achievement will also position Tanzania as a regional hub in energy production and reliability.

Current Status:

The hydropower project has already commissioned four plants. Insights from the assistant commissioner for energy development at the Ministry of Energy show promising results. Mr Styden Rwebangila noted that the fifth turbine is undergoing final testing and will be operational imminently. He also stated that to date, the four operational turbines are generating a combined 940MW. โ€œThe fifth turbine is set to be switched on soon, bringing us closer to the target of activating all nine turbines by June next year.โ€

Project Summary

Location: Tanzania

Capacity: 2GW

Number of Turbines: 9

Project Duration: 1 year

Cost of Project: US$2 Billion

The Significance of the Julius Nyerere Hydropower Project

The Julius Nyerere hydropower project has a focus set in stone, aiming to achieve various goals. In addition to supplying electricity to Tanzania, it also aims to control floods along the Rufiji River. Moreover, it aims to ensure that environmental conservation activities in the area can be managed and maintained. The implementation process encompasses the main dam, the subsidiary dams, the intake works, the water flow tunnels, the electricity distribution station, and the construction of a permanent bridge spanning the Rufiji River. The successful accomplishment of such projects proves the project’s whole-scale nature and ability to have a social and economic impact on the Tanzanian landscape once finished.

Julius Nyerere Hydropower Project
The Julius Nyerere hydropower project has a focus set in stone, aiming to achieve various goals

The project’s main component, the hydroelectric power plant and the centerpiece of the plant itself, is shaping up towards completion. The fact that three of the nine turbines have been installed is remarkable. Moreover, each turbine is already running and generating 235 megawatts of electricity in the Tanzanian national grid. Most parts remain the installation of the remaining turbines. It also includes placing the last concrete works for the whole structure. This signifies that the project is moving towards its final envisioned purpose.ย 

Also read:

Kikagati Hydroelectric Power Project Commissioned as Tanzania-Uganda Joint Power Project Achieves Major Milestone

The State of Affairs Regarding the Julius Nyerere Hydropower Project

Once fully completed, the Julius Nyerere hydropower projectโ€™s nine turbines will each produce 235MW. This translates to over 2GW of electricity, providing a surplus to the nation’s citizens. Furthermore, this achievement is expected to end Tanzania’s power rationing era. โ€œAs of November, 22, 2024, the countryโ€™s maximum electricity demand reached 1,842MW. This is slightly up from 1,839MW the previous day,โ€ noted Mr Rwebangila. He also explained that the peak demand often occurs in the evenings. When in full operation by mid-2025, the project will meet Tanzaniaโ€™s demands and generate enough for export.

Julius Nyerere Hydropower Project
Once fully completed, the Julius Nyerere hydropower projectโ€™s nine turbines will each produce 235MW.

The surplus capacity is important in the governmentโ€™s ambitious plan to increase national power generation. The nation seeks to increase its power generation to 5GW by 2025. Moreover, the government plans to achieve this by leveraging hydropower and natural gas. The surplus will facilitateย the Tanzania Electric Supply Company (Tanesco). It is mandated to oversee 98 percent of electricity production in the country. Furthermore, it isย to eliminate outages and facilitate regional energy trade.

Project Overview

The dam is a key component of the hydropower project. It is 1025 meters long and has a storage capacity of 34 billion cubic meters. The reservoir has collected 33 billion cubic meters of water, more than the minimum operating level needed for the turbines to work properly. This reservoir provides a crucial water resource and a flood control system based on the Rufiji River. Besides, the successful completion of the 400 KVA distribution and connection station has made the project possible to be integrated into the Tanzanian national grid. Therefore, it is possible to transmit electricity smoothly and to meet the growing energy needs of the region. Julius Nyerere Hydropower Plant is also involved in the infrastructural development of the permanent roads.

It is almost entirely constructed, with the final layers and paving completed. These roads are a must for access to the hydropower plant and dam and for enhancing connectivity within the surrounding area. From start to finish, the project’s team has strictly followed the most rigorous quality standards, which resulted in the durability and sustainability of the infrastructure. Hence, the successful realization of the Julius Nyerere Hydropower Project will be the beginning of a new era in Tanzania’s energy sector and general development, providing a trouble-free supply of electricity and fostering sustainable growth for years to come.

Also Read:

Magufuli Bridge Project Currently Under Construction in Tanzania.

Tanzaniaโ€™s Afcon Dreams Soar as Monumental Sh286 Billion President Samia Hassan Suluhu Stadium Project Takes Off