Dualization work of Calabar-Itu-Ikot Ekpene road in Nigeria resumes

Home » News » Dualization work of Calabar-Itu-Ikot Ekpene road in Nigeria resumes

Dualization works of Calabar-Itu-Ikot Ekpene federal road project linking the state with Cross River state in Nigeria has resumed.

The road, which was constructed in the 70s, spans through Akwa Ibom and Cross River states. The Akwa Ibom section of the road is 12.2 km, while the Cross River axis from Odukpani to the gas plant is 9.7 km.

Dualization works of Calabar-Itu-Ikot Ekpene federal road project linking the state with Cross River state in Nigeria.

The road, which was constructed in the 70s, spans through Akwa Ibom and Cross River states. The Akwa Ibom section of the road is 12.2 km, while the Cross River axis from Odukpani to the gas plant is 9.7 km

Calabar-Itu-Ikot Ekpene road

The project site located between Ekim and Ididep villages in Itu local government area along Ikot Ekpene Odukpani in Akwa Ibom has been deserted by the incumbent contractor Julius Berger. Currently it is now almost impassable thereby hampering the free and smooth movement of vehicular movements between the two sister states.

The project contract was awarded by the Federal Ministry of Power, Works and Housing at the heat of the electioneering campaigns to mobilize votes in the South-South for the second term of President Muhammadu Buhari. Design Construct Ltd is the supervising consultant while Julius Berger Nigeria Plc, the portfolio contractor.

Residents in the area raised concerns over the project halt and lamented that currently it is now almost impassable thereby hampering the free and smooth movement of vehicular movements between the two sister states. Only two kilometer was worked on.

“All the equipment mobilized to the site before the general election have been removed by the company without any explanation to the security men in the premises. The result is owing backlog of salaries to workers working on the project,” stated area resident.

From Ididep to Ekim Itam leading to Ekoriko junction, a cyclist Mr Uduak Akpan Udoh complained that the potholes left on the road by Julius Berger has worsened the condition of the road for both motorists and pedestrians.

 

1 thought on “Dualization work of Calabar-Itu-Ikot Ekpene road in Nigeria resumes”

  1. Comment:that contract was stop due to 30% of the money was only paid since then the fedral govt has done nothing about it worker was sacked, and the site was close since than it going to two years plus

Comments are closed.