The Journey With AUS project hit reached another milestone when on May 12, city and airport officials launched construction on the Atrium Infill Project at the Barbara Jordan Terminal in Austin-Bergstrom International Airport (AUS). The project will add 12,000 square feet to the Arrivals and Departures Hall by enclosing the current open-air atrium above the baggage claim area.

Relieving Congestion for Growing Passenger Demand

The expansion is aimed at increasing space for TSA queuing and airline ticketing counters, areas that often see long lines, particularly during peak travel days. The airport has experienced record-setting growth, with monthly traveler numbers exceeding 2 million in recent years.

Art and Infrastructure Combined

The new area will include a public art installation from local muralist Josef Kristofoletti and artist Matthew Mazzotta, enhancing the terminal’s aesthetic appeal while serving practical purposes.

Construction Impact and Timeline

During construction of this phase of the Journey with AUS project, travelers should expect temporary construction walls and noise, though no disruptions to TSA operations or flight schedules are anticipated. The TSA Checkpoint 2 West exit will be reconfigured, and the beloved Barbara Jordan statue in baggage claim will be enclosed for protection and reunveiled in 2026.

Also read:

Milwaukee Mitchell Airport modern terminal construction

DFW International Airport Expansion Gets $4 Billion Boost from American Airlines

US$200m Hector International Airport Expansion project progress

Funding the Expansion

The total project cost is $50 million, funded through:

  • $25 million from the federal Infrastructure Investment and Jobs Act

  • The remainder from airport reserves, operating revenue, and future bonds

  • No local tax dollars are being used

Atrium Infill Project – Fast Facts

Start Date: May 12, 2025
Estimated Completion: 2026
New Space Added: 12,000 sq. ft.
Purpose: Expanded TSA and ticketing areas
Federal Funding: $25 million (Infrastructure Investment and Jobs Act)
Remaining Funding: Airport reserves, revenue, bonds
Taxpayer Funds Used: None
Public Art: By Josef Kristofoletti and Matthew Mazzotta
Construction Impact: Minimal; TSA and flights unaffected

What is the Journey With AUS Project?

The Journey With AUS project is a long-term transformation initiative by Austin-Bergstrom International Airport (AUS) aimed at modernizing and expanding airport facilities to meet growing passenger demand. As one of the fastest-growing airports in the U.S., AUS is investing in near-term improvements and long-term infrastructure to improve traveler experience, operational efficiency, and capacity.

Key near-term projects, many already underway, include the installation of a new baggage handling system capable of processing 4,000 checked bags per hour, expansion of TSA Checkpoint 3 with up to eight lanes, and a 13,000 square foot ticketing atrium infill to ease passenger flow. The West Gate Expansion will add three new gates and enhanced passenger amenities such as more restrooms and quiet spaces, while improvements to international arrivals aim to speed up customs processing with new carousels and booths.

The long-term vision includes a brand-new Concourse B, connected by an underground tunnel to the Barbara Jordan Terminal. This midfield expansion will include at least 20 new gates, lounges, concessions, and expanded baggage infrastructure. A new Arrivals and Departures Hall will centralize security and check-in while replacing the Red Garage and relocating roadways. A 7,000-space Yellow Garage and new midfield taxiways are also planned.

Importantly, the Journey With AUS program is not funded by local Austin taxpayers. Instead, funding comes from airport revenues, FAA grants, cash reserves, and future bonds. Airline partners are key stakeholders, and full implementation depends on their support and collaboration.

This comprehensive development effort is designed to evolve AUS into a future-ready airport, with phased project completions extending through 2030 and beyond.