Rehabilitation of Nyendo-Bukakkata road in Uganda delayed

Home » News » Rehabilitation of Nyendo-Bukakkata road in Uganda delayed

The rehabilitation of the Nyendo-Bukakkata road in Uganda has been delayed by heavy rainfall and delay in the release of funds according to engineers tasked with the project. The government of Uganda had earlier promised to tarmac the 41km road that has been in bad condition for the last two decades; actual construction began in June 2019 after President Museveni broke ground for the project.

The road which connects Masaka to Bukakkata and Kalangala Islands is only 5% complete after five months of work. According to the project manager Mr. Alfred Tugume, construction works cannot advance as anticipated due to unavailable funds and the risk of heavy rainfall. However, Mr. Tugume said they are working to see the project completed on time.

Rehabilitation works

Works on the road include clearing shoulders, removal of the existing top surface, compacting, cover with gravel and tarmac. The contractor is expected to complete the work in 24 months. “We are behind schedule but we are hopeful that we will be able to complete the project on record time and hand it over to the government,” said Mr. Tugume.

Also Read: Construction of Mukono-Katosi-Nyenga road in Uganda, over 70% complete

In addition, Mr. Tugume said the slow progress of National Water and Sewerage Corporation and Umeme in relocating their services has also affected their work. “It is now good that the utility providers have relocated their services such as water pipes, electricity poles and telephone lines,” he added.

Once complete the road will help boost the tourism and farming sectors which are the major economic activities in the area. On the other side, Uganda National Roads Authority (UNRA) land valuer Mr. Moses Kintu has cautioned local residents against making false claims on compensation which have already been completed.