Home » Energy » Wind power » Orlen Neptun Advances Baltic East Wind Project with Transmission Permits

Orlen Neptun Advances Baltic East Wind Project with Transmission Permits

Home » Energy » Wind power » Orlen Neptun Advances Baltic East Wind Project with Transmission Permits

Baltic East wind farm has secured key offshore transmission permits through developer Orlen Neptun. These permits allow for the development of the submarine cables and offshore substation infrastructure that will connect the future 1 GW wind farm to the national grid. This progressive permit also marks a significant milestone in Poland’s expanding offshore wind sector.

The newly granted transmission permits also signals the overcoming of major regulatory hurdles for Baltic East. It also signals the project’s advancement toward engineering, financial structuring, and eventual construction.

Located on the Slupsk Bank in the Baltic Sea, Baltic East is being developed by Orlen Neptun, a subsidiary of the Orlen Group. This is a standalone project separate from Baltic Power offshore wind farm, the 1.2 GW joint venture between Orlen and Canada’s Northland Power.

Baltic East Offshore Wind Project Factsheet

Developer: Orlen Neptun

Location: Slupsk Bank, Baltic Sea, Poland

Proposed Capacity: 1,000 MW

Latest Milestone: Transmission permits approved for subsea cables and offshore substations

Scope of Permit: Offshore export cables and substations linking the wind farm to the national grid

Development Status: Pre-FID. Design and engineering phases expected to follow

Orlen Neptun Advances Baltic East Wind Project with Transmission Permits
The project now expects more approvals henceforth.

Baltic East Offshore Wind Project Timeline

Pre-2023

Orlen Neptun secures concession rights on the Slupsk Bank.

Initial wind resource assessments and seabed surveys conducted.

2023-2024

Environmental and technical feasibility studies continue.

Application for offshore transmission infrastructure permits submitted.

2025

Transmission permits granted for export cables and substations.

Project advances toward engineering and financial close preparations.

2026 onward

Final Investment Decision (FID) expected.

Procurement of turbines and foundations. Grid connection works also expected to start.

Target (year) for full construction and commissioning phase. However, largely depends on progress of regulatory and financing milestones.

What to Expect of the Baltic East Offshore Wind Project

The project continues to strengthen Poland’s ambition to install 11 GW of offshore wind by 2040, contributing to regional energy security. Baltic East offshore wind project also complements Orlen’s Baltic Power project. And, with transmission permits secured, Orlen Neptun is now positioned among the country’s more advanced offshore developers.

The project now expects more approvals henceforth. These include environmental approval for turbine placement, supply-chain capacity, and long-term power offtake arrangements.

Leave a Comment