Tema Motorway Grade Separation project timeline and what you need to know

The Tema Motorway Grade Separation project is not a stand alone project. It is going to bring a lot of benefits in two areas: It is going to create the Tema Arterial Roads and Tema Motorway Project. Upon completion, the Tema arterial roads linking this roundabout to the ongoing port expansion being undertaken by Meridian Port Services would have come to an end. The plan is to open up all arterial roads from this roundabout to link the port expansion project through the Tema Hospital road into a dual two-by-three lane road.

At the same time it will link Tema Motorway with the Tetteh Quarshie interchange in Accra, and the project is designed in such a way that by the time this particular project comes to a close the Tema motorway, as part of the Abidjan-Lagos project, which is being turned into a 6 lane dual carriage highway, would have also come to an end and it has been remodeled and redesigned to take the current congestion at the Tetteh Quarshie interchange.

The Motorway forms an integral part of the Trans-Africa Highway, stretching from Lagos through Lomé, Accra, and Abidjan to Dakar, and effectively serves as the junction to the Sub- region and the Grade Separation forms part of the Improvement of Ghanaian International Road Corridors project.

Also Read: Kazungula bridge project timeline and all you need to know

Project timeline
2018

Phase One of the Grade Separation project, began in February and was expected to come to completion in 28 months. This phase will see the construction of a 2.1km three lane dual carriageway with 730m underpass on the National route N1; improvement of approximately 1.9km two lane dual carriageway on the National Route N2 from the Ashiaman Roundabout onto the Harbour Road; construction of Service Road Ramps, retaining wall and box culvert, road base and pavement; construction of Pedestrian Bridges; and provision of adequate Road Safety furniture to safeguard lives and property.

The Japanese government is providing the funding of approximately US $55.6m through the Japan International Cooperation Agency (JICA).

Phase Two of the project, comprises the construction of a flyover on the Akosombo-Tema Harbour Road. The project will also conduct detailed design improvements for the rehabilitation of National Trunk Road N8 in the Central Region.

2020

In June, it was announced that the Tema Motorway Interchange is to have a police post constructed nearby. The proposed police post will be strategically placed and purposefully meant to ensure that the security for the public within that area is improved and most importantly to help with traffic management on the motorway.

It will have a control tower to help with traffic management and fasten response in case of any road crashes and accidents at the heart of Tema.

In July, it was announced that the second phase of the Tema Motorway Interchange project is expected to commence in September, following an agreement signed between the governments of the West African country and that of Japan.

The agreement was particularly signed by the Ambassador of Japan to Ghana, Mr. Himeno Tsutomu, and the Deputy Minister of Foreign Affairs and Regional Integration, Charles Owiredu.

In late October, the Minister for Roads and Highways, Kwesi Amoako Attah, disclosed that a Portuguese Contractor will begin work to expand the Accra-Tema Motorway to six lanes before the end of the year. The Minister further announced that the Tema Roundabout to Aflao road will be dualized with 3 interchanges; and the Tema Roundabout to Akosombo road will also be dualized.

In late December, the Government of the Republic of Ghana through the ministry of Roads & Highways in a statement announced that it has signed a contract for the design and construction of the Accra-Tema Motorway and extensions project, from the Tema Interchange through Apenkwa Interchange to Neoplan Junction.

The contract was signed with, Mota-Engil- Engenharia E Constructao Africa S. A., a division of Mota-Engil, a Portuguese group in the sectors of civil construction, public works, port operations, waste, water, and logistics, following the approval of the Public Procurement Authority and the Central Tender Review Board.

The scope of the works under the contract

The reconstruction and expansion of the existing 19.5km motorway into a two-lane dual carriageway for the freeway and a three-lane dual carriageway for the urban highway are among the key scopes of the project. The freeway will remain concrete surfacing, whilst the urban highway will be in asphaltic concrete with paved shoulders.

Other works include the reconstruction of the Tetteh Quarshie Interchange to Apenkwa Interchange (5.7km) into a six-lane dual carriageway with Asphaltic Concrete surfacing and reconstruction of Tesano Junction – Neoplan Junction (2.5km) into a three-lane dual carriageway in the asphaltic concrete surfacing.

2021

In late February, Minister of Roads and Highways-designate, Kwesi Amoako Atta, defended the government’s decision to award the US $570m Accra-Tema motorway contract to a sole sourced construction firm, Mota-Engil Engenharia Construcao Africa S.A.

According to him, the technical competence and financial viability best places the company to execute the project, which has been on the drawing board for several years. “This is the recommendation by the technical group majority of which were not from the Roads Ministry. We have gone through a public private partnership process and settled on a proven competent contractor to execute the project,” Mr Amoako Attah told the Appointments Committee of Parliament.

The project, which was earlier pegged at US $470m under a public private partnership agreement, had to be renegotiated for the contractor to solely fund the project. The Minority in Parliament had called for the cancellation of the project, alleging that it did not receive parliamentary approval and had no local component.

In late March, the Japanese government appealed to the government of Ghana to extend tax waivers to some third nationality suppliers in order to pave way for the commencement of phase II of the Tema motorway project.

It has emerged that phase II of the project which was scheduled to begin in the last quarter of 2020 is being delayed due to the waiver demand.

If you have a remark or more information on this post please share with us in the comments section below