PORTS Technology Campus Factsheet
Project NamePORTS Technology Campus
LocationPiketon, Pike County, Ohio
Project TypeArtificial Intelligence Data Center, Power Generation, and Grid Infrastructure Project
GroundbreakingMarch 20, 2026
Latest DevelopmentOn June 16, 2026, the Federal Permitting Improvement Steering Council granted FAST-41 coverage to the project. Making it the first FAST-41 project in the high-performance computing, advanced computer hardware and software sector.
Total Estimated Investment$67.2 billion
AI Data Center Campus InvestmentMore than $30 billion, funded and operated by SoftBank Group.
AI Data Center Capacity10 GW
Natural Gas Power Generation Investment$33 billion
Power Generation Capacity9.2 GW of natural gas generation.
Power Generation OwnershipThe U.S. Government will own the generation facilities, while funding comes in part through the U.S.-Japan Strategic Trade and Investment Agreement.
Grid and Transmission Investment$4.2 billion
Transmission InfrastructureNew 765-kV high-voltage transmission lines and associated grid upgrades through AEP Ohio.
Project SiteApproximately 2,700 acres of private land adjacent to the DOE Portsmouth Site.
Construction ScheduleDevelopment will occur in phases. The first phase is an 800 MW AI data center scheduled to begin construction in 2026.
Employment Impact35,000 construction jobs and 2,500 operating jobs.
Community BenefitsSB Energy has committed $40 million through a Community Benefits Agreement in collaboration with local organizations.
Ratepayer ImpactSB Energy states it will fund 100% of grid upgrades and new transmission infrastructure, with no cost passed on to Ohio ratepayers.
Project PartnersSoftBank Group, SB Energy, U.S. Department of Energy, U.S. Department of Commerce, and AEP Ohio.




Leave a Reply