Project Factsheet:
NameProject Pegasus
LocationLaGrange
Estimated Investment Value$8 Billion
Project TypeHyperscale data center campus
Timeline
2026Google confirms involvement and project progress
ConstructionOngoing
Operational timelineNot publicly specified
Site & Scale
Location~70 miles southwest of Atlanta
Initial Power Capacity32 MW (planned expansion underway)
CampusLarge-scale hyperscale data center development
Water Usage~2 million gallons per day (estimated)
Project Teams
Developer/OperatorGoogle
Local PartnerCity of LaGrange
Infrastructure Scope
Data center campus supporting cloud and AI workloads
Power and utility infrastructure funded by Google
Expansion of local grid and utility systems
Industrial-zone development with supporting facilities
Strategic Objectives
Expand Google’s data center footprint in the U.S.
Support services such as Search, Maps, and YouTube
Leverage Georgia’s data center growth and incentives
Strengthen long-term infrastructure partnerships
Challenges
High water consumption concerns from residents
Pressure on local utilities and transmission systems
Community and environmental scrutiny
Current Status
Construction progressing at Pegasus Parkway site
Google has confirmed full infrastructure cost coverage
Project advancing as part of Georgia’s data center expansion boom