The Bab Gas Cap project has reached a significant procurement milestone after contractors submitted technical bids for an estimated $8 billion gas development in Abu Dhabi, United Arab Emirates. The submissions advance plans for a major gas-processing facility designed to handle additional production from four underdeveloped reservoirs.
Furthermore, the development will expand Abu Dhabi’s capacity to process natural gas and support the United Arab Emirates’ long-term energy security objectives. ADNOC Gas is overseeing the main processing infrastructure, which will handle approximately 1.85 billion cubic feet per day (bcf/d) of additional raw gas. The latest submissions follow an extended tendering period that allowed competing engineering contractors to finalize their technical proposals.
The development represents an important investment in the UAE’s upstream gas infrastructure. It will also create demand for complex engineering, procurement and construction services across several project packages.
Bab Gas Cap Project Advances Through Four Construction Packages
ADNOC Gas has divided the Bab Gas Cap project into four engineering, procurement and construction (EPC) packages. This structure separates the processing plant from supporting infrastructure and associated construction activities.
Package 1 covers the main Bab gas-processing plant. Meanwhile, Package 2 covers early civil works required to prepare the development site.
Package 3 focuses on the pipeline network, while Package 4 covers non-process facilities and associated infrastructure. Consequently, the procurement strategy coordinates several construction interfaces within the wider development.
ADNOC Gas issued the main processing plant tender on June 25, 2026. However, contractors initially faced a July 17 technical submission deadline. The company subsequently extended that deadline by four months to November 16, 2026.
The main plant tender has attracted international engineering contractors through consortium arrangements. The competing teams include Larsen & Toubro Energy Hydrocarbon with Petrofac Emirates. Technip Energies has partnered with JGC Corporation and Sinopec. Additionally, Tecnimont has joined China Petroleum Engineering and Construction Corporation (CPECC).
These partnerships combine international engineering expertise and construction capabilities. However, technical bid submission does not constitute a contract award. ADNOC Gas must evaluate the proposals before proceeding with contractor selection and subsequent commercial decisions.
Bab Gas Cap Project Targets 1.85 Billion Cubic Feet Daily
The proposed facility will address processing limitations at ADNOC’s existing Habshan complex. Its current processing trains cannot accommodate the additional volumes expected from the Bab gas cap reservoirs.
The development targets four reservoirs: Thammama A, Thammama B, Thammama F and Thammama H. Thammama A, B and H could collectively deliver approximately 1.45 billion cubic feet daily. Meanwhile, Thammama F could contribute another 396 million cubic feet daily.
Together, these reservoirs could supply approximately 1.85 billion cubic feet daily. Therefore, the new processing infrastructure will provide the capacity required to accommodate the additional production.
ADNOC Gas plans to construct the processing plant approximately 170 kilometers from Abu Dhabi city. Associated infrastructure will include pipelines, ancillary facilities and specialized gas-treatment systems.
The technical scope also includes acid gas removal, dehydration and natural gas liquids recovery. Furthermore, the design incorporates sulphur recovery and tail-gas treatment facilities.
ADNOC Gas awarded the front-end engineering and design (FEED) contract to Australia’s Worley in December 2024. The assignment covers more than 1.2 million engineering man-hours. It represents the largest engineering assignment ADNOC Gas had awarded at that time.
The development also supports ADNOC Group’s objective of increasing upstream production capacity by 2030. However, ADNOC Gas indicated in August 2026 that it was approaching the final investment decision cautiously. Consequently, the technical submissions represent an important procurement milestone rather than confirmation of full construction authorization.
Bab Gas Cap Project Development and Investment Outlook
The wider development also involves an upstream concession covering the production of gas from the Bab reservoirs. ADNOC holds a 60% participating interest, while international energy companies hold the remaining interests.
The partnership includes TotalEnergies, BP, China National Petroleum Corporation and other international investors. This arrangement supports the upstream development that will supply the proposed processing infrastructure.
Meanwhile, the four-package procurement approach allows ADNOC Gas to advance separate construction components. The technical evaluation will help establish the contractors’ ability to deliver the project’s demanding engineering requirements.
The project is part of a wider expansion of natural gas infrastructure across the Middle East. Saudi Arabia is pursuing a similar strategy through the Jafurah sixth expansion phase, where contractors are preparing bids for two gas compression plants.

Project Fact Sheet
Name: Bab Gas Cap Development Project.
Location: Bab onshore field, approximately 170 kilometers from Abu Dhabi city, United Arab Emirates.
Estimated project investment: $8 billion.
Developer: ADNOC Gas.
Upstream operator: ADNOC Onshore.
Sector: Oil and gas infrastructure and natural gas processing.
Status: Technical bids submitted; contractor evaluation and investment decision remain outstanding.
Main construction component: Greenfield natural gas processing plant.
Processing capacity: Approximately 1.85 billion cubic feet of additional raw gas daily.
Reservoirs: Thammama A, Thammama B, Thammama F and Thammama H.
EPC Packages
- Package 1: Main gas-processing plant.
- Package 2: Early civil works.
- Package 3: Pipeline network.
- Package 4: Non-process facilities and associated infrastructure.
Processing facilities: Acid gas removal, dehydration, natural gas liquids recovery, sulphur recovery and tail-gas treatment.
FEED consultant: Worley.
Main plant tender issued: June 25, 2026.
Technical bid submission deadline: November 16, 2026.
Development objective: Expand UAE gas production and processing capacity while supporting long-term energy security.
Project Team
Developer: ADNOC Gas.
Upstream operator: ADNOC Onshore.
Majority concession holder: ADNOC – 60%.
Concession partners:
- TotalEnergies – 10%.
- BP – 10%.
- China National Petroleum Corporation International – 8%.
- Japan Oil Development Company Onshore – 5%.
- China ZhenHua Oil – 4%.
- Korea GS E&P – 3%.
FEED consultant: Worley.
EPC bidding consortiums:
- Larsen & Toubro Energy Hydrocarbon and Petrofac Emirates.
- Technip Energies, JGC Corporation and Sinopec.
- Tecnimont and China Petroleum Engineering and Construction Corporation (CPECC).