Rail Baltica, the largest rail to be constructed in Baltic Countries in over 100 years

Home » Biggest projects » Rail Baltica, the largest rail to be constructed in Baltic Countries in over 100 years

Fegda and Tilsta of Lithuania will build a new substructure for a double-track railway as well as engineering structures on the Rail Baltica section between Kaunas and the Lithuanian-Latvian border. The Rail Baltica project spans 392km in Lithuania, 265km in Latvia, and 213km in Estonia. Totally, it has a length of 870km.

LTG Infra announced that the joint venture partners had secured two tenders worth approximately €165.54 million. The construction work is in Jonava District. LTG Infra is in charge of project implementation in Lithuania. The Šveicarija-Žeimiai section contract is valued at €87.88m. Additionally, the Žeimiai-Šėta section contract is worth €77.6m.

The Šveicarija–Žeimiai section will be completed in one and a half years, and the Zeimiai–Šėta section will be completed in two years. Fegda and Tilsta will build a 17.7km substructure and engineering structures on the 10km section. It will stretch from Šveicarija to Žeimiai, as well as the section from Žeimiai to Šėta.

Read Also: Plans approved for Keadby 3 carbon capture power station in UK

Construction works on the Rail Baltica project

All railway works will be completed without the installation of the superstructure. These works include the preparation of land and parcels of land and the installation of a railway drainage system. Others include the construction of a protective fence, as well as the implementation of a portion of the service roads.

During the course of the contracts, railway bridges, wildlife crossings, sound barrier walls, and other engineering structures will be built. The reconstruction and repairs of the telecommunications and electricity networks and the reconstruction of the state district and national roads will be carried out during the construction of the substructure.

“The most developed section of Rail Baltica is already under construction and be much expanded,” said Dovydas Palaima, general manager of LTG Infra Rail Baltica Management. “In 2024, we intend to begin major construction work on the railway to Panevėžys. This is as well as the majority of the preparations for the railway’s construction on the other sections.”

Rail Baltica Project Overview

Also known as Rail Baltic in Estonia, Rail Baltica is an ongoing greenfield railway infrastructure project in the Baltic Countries. It is meant to link Finland, Estonia, Latvia, and Lithuania with Poland.

The project envisages a continuous rail link from Tallinn in Estonia to Warsaw in Poland. It consists of links via Riga in Latvia, and Kaunas and Vilnius in Lithuania. The total length in the Baltic States is 870 kilometers. 213 kilometers are within Estonia, while 265 and 392 kilometers are within Latvia and Lithuania respectively.

It will consist of three multimodal freight terminals. These will be constructed in Estonia’s Muuga Harbour, Salaspils in Latvia, and Kaunas in Lithuania. It will also consist of seven international passenger stations. These will be located in Tallinn, Pärnu, Riga, Riga Airport, Panevežys, Kaunas, and Vilnius. The project has potential regional stations and connections to airports and seaports.

From Poland, Rail Baltica will connect will the European standard gauge rail network. It is one of the priority projects of the European Union. In addition, it is a part of the North Sea-Baltic Corridor of the Trans-European Transport Networks (TEN-T).

Its purpose is to provide passenger and freight service between the participating countries. Additionally, it intends to improve rail connections between Central and Northern Europe, specifically the area in the Southeast of the Baltic sea. Furthermore, Rail Baltica will be a catalyst for building the economic corridor in Northeastern Europe.

Summary

Name:                 Rail Baltica

Type:                   High-speed rail

Length:               870 kilometers

Max. speed:         249 km/h (passengers), 120 km/h (freight)

Construction:       2019-2029

Reported earlier

Dec 2020

Rail Baltica Central Hub construction begins

Construction of Rail Baltica Central hub in Riga, Latvia has officially begun on schedule. This marks a significant milestone as it will be the largest infrastructure project in the region in 100 years. The project includes a new central station building, a major railway bridge on the Daugava river, and various rail infrastructures.

The project, financed by the European Union (EU) and the Republic of Latvia, will integrate the Baltic States; Helsinki, Tallinn, Riga, Vilnius, and Warsaw into the European rail network. The construction site was formally opened by senior representatives of Rail Baltica, the project implementer, and the supervisory team of civil engineers. They welcomed the builders and congratulated them on the commencement of construction work.

Also Read: Rail Baltic project exceeds budget estimations.

Central Hub in Riga, one of the most important construction phases of Rail Baltica

The Central Hub in Riga represents one of the most important construction phases of the Rail Baltica Project. The latter includes the reconstruction of the Riga Railway Station complex and the construction of a railway bridge across the River Daugava.

In addition, Rail Baltica Project includes the construction of the European standard gauge tracks and the removal of embankments. The construction of an overpass and the construction of the adjacent infrastructure are also a part of the project. BESIX is responsible for the design and build of it, as part of a joint venture with SIA RERE BŪVE.

Earlier, the JV BERERIX engineers successfully saw the complex design of the future railway station pass the wind tunnel and wind comfort tests. Moreover, the design received the final approval for the master designs. The team is now eager to make the Rail Baltica project visible and tangible for citizens and guests of Riga. This will achieve while strictly following all restrictive measures to curb the spread of COVID-19.

The construction site is set up to enable continuous work and social distancing for about 100 workers employed on the site who are working day and night shifts. In order to meet all requirements, prevent the carrying and spreading of COVID-19 on the building site, and ensure a timely construction process of the Central Hub in Riga according to Xavier Debruche, one of the project leaders.

Aug 2022

Rail Baltica: Tender announced for Kaunas Urban Node to Vilnius Urban Node stretch

A new tender for design and design supervision services for the Kaunas Urban Node to Vilnius Urban Node portion of Rail Baltica has been revealed. This is according to RB Rail, a Rail Baltica joint venture. LTG Infra, the company in charge of putting Lithuania’s Rail Baltica project into action, will help with the project’s execution.

Applications for the qualification stage are expected to be received by October 14 of this year. The contract on the other hand is anticipated to be signed in the second half of 2023.

Read Also: Refurbishment almost complete on Southampton’s Redbridge Causeway

Scope of the Kaunas Urban Node to Vilnius Urban Node contract 

The contract covers the provision of design and design supervision services to construct railway track substructures, superstructures, and related civil systems. All this will be carried out on the stretch that features 65 km of double-track 1,435 mm-gauge railroads.

Particularly, the contract covers the rehabilitation of about 16 km of the existing 1,520 mm-gauge railroads. Additionally, it covers the construction of  15 culverts, additional infrastructure, and utilities. Moreover, the contractor will build ten road viaducts, one road tunnel, 13 railway viaducts, eight wildlife crossings, and three passing loops.

Speaking on this initiative, Marius Narmontas said they will promote transparent competition in the Rail Baltica procurements, therefore, improving the best practice. Narmontas is the head of RB Rail Lithuania. He added that the re-launch will help to integrate improved qualification standards into the procurement rules permitting larger market participation.

RB Rail and Esri recently signed an enterprise agreement. This was in order to integrate geographic information system (GIS) software across all project units.

Nov 2022

Construction procurement announced for Rail Baltica Ãœlemiste terminal in Estonia

The passenger terminal at Rail Baltica Ãœlemiste will be named Linda | Rail  Baltica

Rail Baltica Estonia has announced the construction procurement for the first stage of the Ülemiste terminal building in Tallinn, Estonia. The tender is expected to cost around €66.5 million.

After the existing railway is demolished, an underground level and other railway facilities will be built. The existing Ãœlemiste railway infrastructure will be rebuilt in order to make room for the Rail Baltic 1,435mm gauge railway. Three bids had been submitted for the reconstruction of the railway infrastructure associated with the joint terminal by the deadline for the construction tender.

The Ãœlemiste terminal project will begin with the demolition of approximately 16.3 kilometers of existing tracks, and then the construction of over 8 kilometers of new 1,520mm gauge railways. It will also include the rebuilding of utility networks that cross the railway and the Kantsi viaduct.

Construction permits have been issued for the completion of the Ãœlemiste terminal project. The majority of the railway work is expected to be completed in 2024. Thus, the contractual work would wrap up in 2026.

Read Also: Contract awarded for U2 and U4 subway lines digital train control system in Germany

Design for Ãœlemiste terminal project

The Ãœlemiste railway infrastructure was designed by OU Reaalprojekt and OU Allspark. Additionally, the terminal was written and designed by Zaha Hadid Architects and Esplan OU.

“We are procuring the construction of the Ãœlemiste joint terminal in stages,” said Rail Baltic Estonia operations head Marko Kivila. “Now that the procurement for the reconstruction of the railway infrastructure has been completed, we can go on with the next stage, which is the construction procurement for the concrete structures under the railway.” In essence, we are acquiring the terminal building’s underground portion.”

The deadline for submitting bids for the construction of railway facilities at the Ãœlemiste passenger terminal has been set for January 5, 2023. If the procurement is completed on time, construction will begin early next year.