Project Factsheet
- Company: Fermi America
- Financier: MUFG Bank (Japan-based; one of the top 10 financial groups all over the world)
- Financing Amount: $500 million
- Purpose: Back 2.3GW first stage of 11GW long-duration power plan.
- Location Focus: Amarillo, Texas (U.S.)
Funding Allocation
- Purchase of three Siemens Energy F-class gas turbines.
- Paying back of an outstanding loan.
- Delivery, construction and logistics.
- Installation of more turbines in the Fermi fleet.
Strategic Objectives
- Provide initial 2.3GW of resilient scalable power.
- Obtain equipment with long lead time.
- Firm near-term execution assurance.
- Place Company as to future level of project financing.
- Scale to 11GW capacity target.
Related Projects
- Project Matador (data center project) supported.
- Project Matador in the progress towards Phase II.
- Aims to power projects without straining Amarillo community.
Executive Statement
- CEO Toby Neugebauer emphasized:
- Early equipment acquisition
- Market positioning
- Accelerated execution (“Fermi speed”)
Current Outlook
- Financing secured
- Waiting to obtain approvals needed to continue to Phase II expansion.
- Prepares Fermi America to deploy scaled energy deployment and finance future round.



Leave a Reply