Justified Data Center Campus in Hawesville, Kentucky Awards Fluor EPC Contract

Home » Buildings » Data Center » Justified Data Center Campus in Hawesville, Kentucky Awards Fluor EPC Contract
Justified Data Center Campus in Hawesville, Kentucky Selects Fluor for EPC Job

Project Fact Sheet for Justified Data Center Campus

LocationHawesville, Hancock County, Kentucky

Project owner and developerTeraWulf Inc.

EPC contractorFluor Corporation

Construction scopeThree data center buildings

Power availabilityUp to 480 MW of grid-connected power announced at the initial project stage

Critical IT capacity401 MW

Contract arrangementEngineering, procurement and construction on a guaranteed maximum price basis

Construction statusEarly works underway

Expected completionPhased ready-for-service delivery from late 2027 through Q2 2028

Major customerAnthropic

Google’s involvementCredit support for anticipated project debt financing

Who is Involved in the Justified Data Center Campus Project?

TeraWulf Inc. – Project owner, developer and digital infrastructure operator.

Fluor Corporation – EPC contractor responsible for engineering, procurement, construction, testing and commissioning.

Google LLC (Alphabet Inc.) – Provides contractual credit support for anticipated debt financing.

Anthropic – Long-term data center customer under approximately US$19 billion in contracted lease commitments.

Source: constructionreviewonline.com All rights reserved. Unauthorized reproduction prohibited.

Featured Companies

Comments

Leave a Reply

Your email address will not be published. Required fields are marked *