Project Fact Sheet
ProjectMeta Beaver Dam data center.
LocationBeaver Dam, Dodge County, Wisconsin, United States.
Developer and ownerMeta Platforms.
Estimated investmentApproximately $1 billion.
Building areaMore than 700,000 square feet.
Project typeAI-optimized data center campus.
General contractorMortenson.
Utility partnerAlliant Energy.
Reported power requirementUp to 220MW.
Supporting energy infrastructureNearly $200 million in planned energy-related infrastructure investment.
Construction statusUnder construction, according to project reporting.
Expected completion2027.
Environmental commitmentsDry cooling, local watershed replenishment and restoration of 570 acres of wetlands and prairie.
Community investment$15 million over ten years for household energy assistance.
Project Team
Developer and OwnerMeta Platforms
General ContractorMortenson
Utility PartnerAlliant Energy
Environmental Restoration PartnerDucks Unlimited
State Economic Development PartnerWisconsin Economic Development Corporation
Local Government PartnerCity of Beaver Dam
Public-Sector PartnerWisconsin State Government