$1 Billion Meta Wisconsin Data Center Advances Toward 2027 Completion

Home » Buildings » Data Center » $1 Billion Meta Wisconsin Data Center Advances Toward 2027 Completion
Meta’s Wisconsin Data Center

Project Fact Sheet

ProjectMeta Beaver Dam data center.

LocationBeaver Dam, Dodge County, Wisconsin, United States.

Developer and ownerMeta Platforms.

Estimated investmentApproximately $1 billion.

Building areaMore than 700,000 square feet.

Project typeAI-optimized data center campus.

General contractorMortenson.

Utility partnerAlliant Energy.

Reported power requirementUp to 220MW.

Supporting energy infrastructureNearly $200 million in planned energy-related infrastructure investment.

Construction statusUnder construction, according to project reporting.

Expected completion2027.

Environmental commitmentsDry cooling, local watershed replenishment and restoration of 570 acres of wetlands and prairie.

Community investment$15 million over ten years for household energy assistance.

Project Team

Developer and OwnerMeta Platforms

General ContractorMortenson

Utility PartnerAlliant Energy

Environmental Restoration PartnerDucks Unlimited

State Economic Development PartnerWisconsin Economic Development Corporation

Local Government PartnerCity of Beaver Dam

Public-Sector PartnerWisconsin State Government

Also read:

Former Homer City Plant to Become a $10 Billion AI Data Center Campus

Meta Plans $10B New AI Data Center in Richland Parish, Louisiana

Source: constructionreviewonline.com All rights reserved. Unauthorized reproduction prohibited.

Featured Companies

Comments

4 responses to “$1 Billion Meta Wisconsin Data Center Advances Toward 2027 Completion”

  1. John Avatar
    John

    I am sick of seeing my electrical bill going up because of these ugly drains on the resources in my city.

  2. Brent H Avatar
    Brent H

    How much will electric bills go up to pay for the electricity this monstrosity will use.

  3. John Avatar
    John

    Wtf is a “digital infrastructure hub”? You mean a bunch of grey warehouses, right? Have fun with the light pollution and the noise rumbling through your body 24/7. And btw, these are dark facilities not factories. There will a couple of guys on site in the few rooms that have the lights turned on. The rest will be handled (when needed) remotely. I say when needed because AI will fill a lot of the break/fix IT demand. They are only there to steal your water and by the time you see how bad the thing is, you won’t be able to pay someone to take your house. Look this stuff up, it’s not conspiracy theory bs, its actually happening to other towns

  4. Steven Scott Avatar
    Steven Scott

    Generational farms bulldozed for “progress” it’s a shame. Data centers shouldn’t exist, theyre an eyesore and drain resources from local communities.

Leave a Reply

Your email address will not be published. Required fields are marked *