Meta Tables Plans for $437M Gas-fired Power Plant to Run its Data Center in El Paso, Texas

Home » Energy » Meta Tables Plans for $437M Gas-fired Power Plant to Run its Data Center in El Paso, Texas
Meta Gas Plant in El Paso

Project Overview

  • Project: Behind-the-meter natural gas plant for data center campus
  • Location: El Paso
  • Developer: Meta Platforms
  • Total Gas Plant Investment: $437 million
  • Data Center Capacity: 1GW campus
  • Power Generation: 366MW modular natural gas plant
  • Generation Units: 813 modular generators
  • Target Operational Date: 2027

Power Structure

  • Behind-the-meter configuration
  • Unconnected to the grid during initial five-year “bridge period”
  • Meta to cover all generation costs during this period

Data Center Development

  • Third Meta campus in Texas (after Fort Worth and Temple)
  • Land acquired via WurldWide LLC affiliate
  • Over 1,000 acres in northeast El Paso
  • First phase investment: $1.5 billion
  • Potential for five total phases
  • Each phase approx. 800,000 sq. ft.
  • Designed for traditional servers and AI-enabled hardware
  • Closed-loop liquid cooling system (zero water use for most of the year)

Regulatory & Community Response

City Action

  • El Paso City Council voted unanimously to intervene in regulatory process
  • Concern: Potential future inclusion of plant costs in general rate base

Community Opposition

  • Sembrando Esperanza Coalition
    • Environmental and economic justice concerns
    • Claims project contradicts earlier renewable energy expectations

Key Issues

  • Fossil fuel reliance vs. renewable energy commitments
  • Long-term utility rate implications
  • Environmental justice concerns
  • El Paso not traditionally a major data center hub

Source: constructionreviewonline.com All rights reserved. Unauthorized reproduction prohibited.

Featured Companies

Comments

Leave a Reply

Your email address will not be published. Required fields are marked *