Project Overview
- Project: Behind-the-meter natural gas plant for data center campus
- Location: El Paso
- Developer: Meta Platforms
- Total Gas Plant Investment: $437 million
- Data Center Capacity: 1GW campus
- Power Generation: 366MW modular natural gas plant
- Generation Units: 813 modular generators
- Target Operational Date: 2027
Power Structure
- Behind-the-meter configuration
- Unconnected to the grid during initial five-year “bridge period”
- Meta to cover all generation costs during this period
Data Center Development
- Third Meta campus in Texas (after Fort Worth and Temple)
- Land acquired via WurldWide LLC affiliate
- Over 1,000 acres in northeast El Paso
- First phase investment: $1.5 billion
- Potential for five total phases
- Each phase approx. 800,000 sq. ft.
- Designed for traditional servers and AI-enabled hardware
- Closed-loop liquid cooling system (zero water use for most of the year)
Regulatory & Community Response
City Action
- El Paso City Council voted unanimously to intervene in regulatory process
- Concern: Potential future inclusion of plant costs in general rate base
Community Opposition
- Sembrando Esperanza Coalition
- Environmental and economic justice concerns
- Claims project contradicts earlier renewable energy expectations
Key Issues
- Fossil fuel reliance vs. renewable energy commitments
- Long-term utility rate implications
- Environmental justice concerns
- El Paso not traditionally a major data center hub