Construction work on Kenya’s Standard Gauge Railway (SGR second phase) from Nairobi to Naivasha will be completed in September 2019. The government is targeting to complete the construction on December 2019 but a review in the plans showed it will be completed three months before the set deadline. “Both the rail and the special economic zone should be operational by the end of 2019,” Transport Principal Secretary Paul Maringa said.
On completion, the 120 km Nairobi-Naivasha line which will cost the taxpayer US $1.5bn will connect to the recently completed stretch from Mombasa port to Nairobi. The project is also expected to eventually connect Nairobi to Kampala via Naivasha, Kisumu and Malaba.
Job protests
In an interview in Mombasa, Prof Maringa said the recent chaos by the Maasai community will not affect the set timeline.
The community had staged protests demanding jobs from the mega project. the protests resulted to the death of one person. The victim was among a group of youth who tried to storm the construction site protesting that locals had not benefited from the project. The ongoing construction faced hitches as bad blood between the local community and the Chinese firm constructing the second phase threatened to boil over.
Skills
The early entry of the Chinese contractor at the SGR line before land owners were compensated caused friction with the local community, resulting in further delay of the endeavor.
However, the PS said the challenges occasioned by the demonstrations have led to serious engagements and networking with local political leadership in Kajiado and Narok counties.
Also read:Â Chinese firm to conduct feasibility studies for SGR expansion in Kenya
“We have developed a consultative framework to ensure that locals feel they are an integral part of the SGR,” he said. He cited lack of skills as a challenge hindering locals from being employed. But he assured them that they would be trained and employed.