Updated April 22, 2026 – Lumsden Point project at Port Hedland in Western Australia has recently entered a more advanced construction phase, with enabling infrastructure now largely in place and civil works almost reaching operational readiness. As of April 2026, the project has hit a major milestone with the completion of a new Great Northern Highway Lumsden Interchange, a four-way road system featuring flyover bridges, an underpass, and dedicated access ramps designed to safely handle oversize vehicles serving the port precinct. The interchange is located at the junction of Pinga Street, Lumsden access road, and the Great Northern Highway which serves as a primary inland corridor to the Kimberley region and Pilbara mining zones.
This upgrade is also an important gateway into the multi-user facility and is intended to support efficient movement of critical minerals exports and renewable energy imports such as wind turbine components. The project is also increasingly defined by its role in enabling diversified trade flows. This is especially particular to battery minerals export and large-scale renewable energy infrastructure import.
With first operations expected around mid-2026, Lumsden Point is steadily transitioning into its final delivery phase. Focus on construction is now shifting toward berth completion, installation of heavy-lift infrastructure, and integration of logistics tenants within the industrial precinct. This will also complete construction work on roads and essential utilities that are over halfway done.

2025 Construction Milestone Snapshot
This latest progress builds on sustained construction momentum through 2025, during which Pilbara Ports advanced key marine and landside works including piling for the future wharves, completion of the causeway linking the logistics hub to the waterfront, and the awarding of major civil contracts for roads, utilities, and services.
Fact Sheet for Lumsden Point Development at Port Hedland in Western Australia – 2026 Update
Location: Port of Port Hedland, Western Australia
Project Owner: Pilbara Ports Authority
Project Type: Multi-user port facility, logistics hub, and common-user export-import precinct
Sector Focus: Critical minerals export, renewable energy infrastructure import, and general cargo
Project Scale and Components:
- Two new multi-user berths (wharves)
- Dredged channel access and turning basins
- New causeway linking port to landside logistics hub
- Integrated road, utilities, and services corridor
- Heavy-lift capable infrastructure for oversized cargo (e.g., wind turbine blades)
- Direct connection to Great Northern Highway via new interchange system
Primary Functions:
- Export of battery minerals (lithium, copper concentrates, etc.)
- Import of renewable energy infrastructure
- Support for direct shipping services to the Pilbara
- Decongestion and capacity expansion of Port Hedland port system
Importance of Lumsden Point Port Development
- Enables diversification beyond iron ore exports
- Supports Western Australia’s energy transition and decarbonization agenda
- Strengthens Australia’s role in global critical minerals supply chains
- Positions Port Hedland as a green energy logistics gateway
Project Timeline
2023–2024: Early Works and Contracting Phase
- Initial seawall construction and dredging works start
- Major civil engineering and marine contracts awarded
- Early enabling infrastructure planning completed
2025: Construction Phase
- Completion of major causeway linking wharf area to logistics hub
- Installation of more than 280 steel piles for wharf foundations begins
- Landside civil works awarded for roads, utilities, services
- Logistics tenants and land allocations begin
- Continued dredging and marine shaping of port basin
Late 2025: Integration Phase
- Expansion of internal road networks and service corridors
- Progress on wharf structural works and logistics hub infrastructure
- Utilities installation across precinct

2026: Commissioning Phase
- March-April 2026:
The Great Northern Highway Lumsden Interchange is complete. The interchange now provides safe heavy-vehicle access for oversize transport. This is an important requirement for wind energy and mining logistics supply chains.
Early operational readiness works are underway across the port precinct.
Marine and landside construction continues toward berth completion and logistics hub activation.
Construction of more than half of roads and essential utilities are complete.
- Mid-2026: First imports expected
- Progressive commissioning of wharf and cargo handling systems
- Final integration of logistics tenants and cargo operators
Who is Spearheading Development of Lumsden Point at Port Hedland in Western Australia
Project Owner
- Pilbara Ports Authority (PPA)
Government Partners
- Government of Western Australia
- Australian Government through Commonwealth funding for Pilbara port upgrades
Contractors
- Ertech Pty Ltd for landside civil works, roads, services, causeway sealing
- Acciona Australia for landside wharves design and construction
- Konecranes for the supply and construction of two state-of-the-art mobile harbor cranes
- Agilitus for Lumsden Point concept design
- Marine construction contractors for wharf piling and dredging
Planning and Delivery
- WA Department of Transport and Ports
- Regional development authorities supporting Pilbara industrial expansion

Lumsden Point Port Expansion Project in Australia Underway
Reported February 28, 2023 – The Lumsden point port expansion project in Australia strives to increase the port’s capacity to export battery metals. These include copper concentrates and lithium. The project also aims to increase the port’s capacity to import renewable energy infrastructure such as blades and wind turbines.
The contract for the project was awarded to MGN Civil. The marine civil contractor specializes in the construction of sea walls alongside ground improvement, land reclamation, and wick drain installation. Right in the Port of Port Hedland, the project will deliver new multi-user facilities and berths. As a result, it will contribute towards further supporting and boosting renewable industries in Australia and overseas.
Read Also: Upgrade of Blue Mountain Rail Line in Australia complete
Lumsden Point Port Expansion Project in Australia to Deliver Lasting Infrastructure
A total of $565 million will be invested into the project by the Federal Government. On the other hand, the Western Australian Government will contribute $96.5 million. The first stage of the Lumsden point port expansion project in Australia will feature the construction of two sea walls. Moreover, the project will also construct a new causeway, which will connect the wharf to a proposed logistic hub.

While commenting on the project, the Prime Minister said that the Federal Government’s investment will help unlock investment as well as trade opportunities. Furthermore, Anthony Albanese added, the investment will further drive Australia’s Net Zero future. Meanwhile, the Federal Minister of Infrastructure. Transport, Regional Development, and Local Government said that the project will deliver lasting infrastructure.
Moreover, Catherine King noted, it will make great use of local materials as well as expertise, especially for the first seawall. Most importantly, the project will contribute to real short-term employment alongside an economic boost. As identified by Infrastructure Australia, a huge portion of the national infrastructure priority features growing the capacity of Pilbara Ports.