Construction is advancing on Toronto’s Don Valley Crossing Bridge, a key component of the Ontario Line rapid transit project. The new elevated bridge will carry Ontario Line trains from the Minton Place tunnel portal across the Don Valley to Thorncliffe Park, forming one of two major crossings over the valley.
Recent work has focused on drilling, piling and foundation construction, with crews preparing and constructing the bridge piers that will support the superstructure. The crossing is designed to connect the underground section of the Ontario Line with the elevated guideway, helping create a continuous 15.6-km rapid transit corridor between Exhibition Place and Don Valley Station. This is as other mega bridge projects continue to advance development, including the Gordie Howe International Bridge that has been recently inaugurated.
Current schedules indicate the Don Valley Crossing structure is expected to be completed in late 2027, supporting the broader Ontario Line program targeted for completion around 2031.

Don Valley Crossing Bridge Project Fact Sheet
Location
- Don Valley, Toronto, Ontario, Canada
- Between Minton Place and Thorncliffe Park
Project Type
- Elevated railway bridge
- Rapid transit infrastructure
Parent Project
- Ontario Line Subway
Owner
- Metrolinx (Government of Ontario)
Project Delivery
- Ontario Line South Civil (Pape Tunnel & Underground Stations)
- Ontario Line Elevated Guideway package
Purpose
- Carry Ontario Line trains over the Don Valley.
- Connect underground tunnel portal with elevated guideway.
- Improve transit capacity across Toronto.
Bridge Type
- Long-span elevated railway bridge
Length
- Part of the Don Valley crossing section (final bridge dimensions have not been publicly released).
Don Valley Crossing Bridge Construction Status
- Foundation and piling works underway.
- Pier construction progressing.
- Superstructure construction to follow.
Expected Completion
- Don Valley Crossing: Q4 2027
- Ontario Line opening: 2031
Involved Companies, Developers and Stakeholders
- Metrolinx (Project Owner)
- Government of Ontario
- Infrastructure Ontario
- Ontario Transit Group (major delivery consortium for the southern civil works)
- Ferrovial Construction
- VINCI Construction Grands Projets
- Janin Atlas
- Rizzani de Eccher
- Parsons Corporation
- City of Toronto
- Toronto Transit Commission (TTC)
Ontario Line’s Don Valley Crossing Bridge Anticipated to Join Iconic Toronto Skyline View
Reported May 11, 2025 – The Don Valley Crossing bridge will be a signature piece of infrastructure in Toronto’s transportation network. The mega infrastructure project commenced construction in 2024 as part of the Ontario Line subway. When finished, it will cross the Don Valley, linking the Crosstown LRT in the north with Exhibition Place in the south. The 15.6-kilometre line includes 15 new stations and will run through the downtown core.
The Ontario Line will cross the Don Valley twice. One is the Lower Don Bridge, a smaller but architecturally significant steel arch bridge. But the Don Valley Crossing bridge will be the more prominent one. Rising 38 metres above the valley floor, its balanced cantilever design will see it become the first high-level crossing to be built in the area since 1927. From the Leaside Bridge’s vantage point, it will be a permanent addition to Toronto’s skyline.
Also read: The $27 Billion Ontario Line in Toronto: Canada’s Largest Project

Significance and Scope of Toronto’s Don Valley Crossing Bridge
The Don Valley Crossing bridge is significant to Toronto’s growing transit system. The bridge will carry subway trains over a deep urban valley, linking communities more effectively. It will also improve daily commutes and showcase scenic city views. Though its concrete form is utilitarian, its scale qualifies it to be a visual icon. Its construction is also an important step towards sustainable urban mobility.

In scope, the bridge is a major undertaking in the Ontario Line project. Its creation involves bridging difficult terrain, preserving existing infrastructure, and incorporating new transportation corridors. The bridge also embodies a marriage of function and legacy, blending engineering imperatives with city-building aspirations.
When completed, it will not only be a vital transit link but also a viewing area, much like the Bloor Viaduct. The project is also anticipated to compliment the construction of the multi-billion-dollar Ontario line. Together with the Highway 413 project currently ongoing, Ontario’s highway network is set to be transformed within the coming years.