Project Factsheet:
- Project Name: Project Ruby Data Center Campus
- Location: Columbus, Georgia
- Estimated Investment Value: $5 Billion+
- Project Type: Campus development of data centers
Timeline
- Site negotiations underway
- Construction to commence 2027 -2030.
- Also 200MW grid capacity by 2029.
- Complete grid scaling until 2034.
Site & Scale
- 987 acres
- Four-building campus proposal.
The overall requested grid connection is 600MW.
Key Developers / Authorities / Partners.
- Development Authority of Columbus – Local development authority spearheading site negotiations.
- Choose Columbus – Regional economic development organization helping to coordinate projects.
- Habitat Real Estate Partners – Negotiating site; also purchaser of the land in Upatoi.
- Atlas Development – Reported project participant; also engaged in data center developments in the state.
- Flint Energies- Electricity company; 600MW grid connection application.
Strategic Objectives
- Make Columbus a significant data infrastructure center.
- Also expand regional tax base
- Provide employment opportunities in the long term.
- Furthermore, it will build stronger data center ecosystem in Georgia.
Power & Infrastructure
- 600MW total power request
- 200MW initial supply target (2029)
- Scalable power supply until 2034.
Current Status
- Energetic land acquisition negotiations.
- Grid capacity negotiations in progress.
- Also no tax incentives are reported to be offered.