Shedgum Gas Expansion Project: Four Bidders Eye Saudi Aramco Gas Works as $1.24bn Package Advances

Home » Energy » LNG » Shedgum Gas Expansion Project: Four Bidders Eye Saudi Aramco Gas Works as $1.24bn Package Advances
Shedgum Gas Expansion Project

The Shedgum gas expansion project is attracting renewed contractor interest as Saudi Aramco advances plans to expand its natural gas compression infrastructure in the Eastern Province. Four international contractors or consortia are expected to compete for the main engineering, procurement and construction (EPC) contract.

The latest competition follows Aramco’s decision to retender the Shedgum gas compression plant package. Consequently, the procurement process presents another major opportunity for international engineering companies targeting Saudi Arabia’s expanding energy infrastructure market. Meanwhile, the wider Shedgum-Uthmaniyah development has recorded significant progress, including a separate $1.24 billion EPC award for the Uthmaniyah compression plant.

Shedgum Gas Expansion Project Attracts Four Contractors

Saudi Aramco reopened the main Shedgum EPC procurement process after cancelling an earlier tendering exercise. According to Upstream, four leading international contractors or consortia are expected to compete for the works.

Larsen & Toubro Energy Hydrocarbon (L&T) and China’s Sinopec feature among the companies associated with the competition. However, publicly accessible reporting does not establish the complete identities of all four prospective bidders.

MEED previously reported that Aramco had entered discussions with L&T concerning the Shedgum gas compression facility package. The Indian engineering company has extensive experience delivering energy infrastructure projects across Saudi Arabia.

Sinopec also features in reporting concerning the wider programme. However, its previously reported involvement concerned a separate pipeline package involving Al-Qahtani Pipe Coating Industries. That consortium subsequently broke up after failing to satisfy Aramco’s requirements.

Therefore, the earlier Sinopec consortium should not automatically be treated as one of the four confirmed bidders. The complete bidder list remains subject to further verification.

The renewed competition comes as Aramco advances several interconnected construction packages. These include compression facilities, gas pipelines and supporting infrastructure.

Shedgum Gas Expansion Project Covers Major Construction Works

The wider development targets increased compression and processing capacity at the Shedgum and Uthmaniyah gas plants.

Currently, Shedgum receives approximately 870 million cubic feet of Khuff raw gas daily. Meanwhile, Uthmaniyah handles approximately 1.2 billion cubic feet daily.

Aramco intends to strengthen both facilities through new compression installations and associated pipeline infrastructure. Consequently, the programme comprises nine EPC and supporting packages.

The packages cover:

  • Shedgum gas compression facility and in-plant works.
  • Uthmaniyah gas compression facility and in-plant works.
  • Shedgum gas compression pipelines.
  • Uthmaniyah gas compression pipelines.
  • Central temporary construction facilities.
  • Early works and site preparation.
  • Operation and maintenance of temporary construction facilities.
  • Plant project inspection and assessment works.
  • Plant project support and associated services.

Meanwhile, Al-Shalawi International Company Trading and Contracting secured the early works and site preparation package.

Arkad Engineering & Construction also emerged as the lowest bidder for the Shedgum pipeline package. These developments demonstrate progress beyond the main compression facility procurement.

Shedgum Gas Expansion Project Supports Saudi Arabia’s Gas Ambitions

The wider programme supports Saudi Aramco’s ambition to increase domestic gas production and processing capacity by 80% by 2030, using 2021 as its baseline.

Additionally, increased gas availability will support electricity generation and industrial development. It will also strengthen supplies for Saudi Arabia’s expanding petrochemical sector.

The Uthmaniyah compression plant package has already advanced to construction. Aramco awarded the approximately $1.24 billion EPC contract to Saipem Nasser Saeed Al-Hajri Contracting Company (SNSH).

SNSH comprises Italian contractor Saipem and Saudi Arabia’s Nasser Saeed Al-Hajri & Partners. Saipem disclosed its share at approximately $1.04 billion, with works scheduled for 42 months.

The award demonstrates the scale of investment supporting the wider development. However, Aramco has yet to announce the successful contractor for the newly retendered Shedgum main EPC package.

Shedgum Gas Expansion

Saudi Arabia’s investment in gas infrastructure also reflects a wider expansion of the global oil and gas processing industry. Similar investment is taking place in China, where CSPC, a joint venture between CNOOC and Shell, committed $8 billion to expand its Huizhou Phase 3 Ethylene and Polycarbonate projects. The development includes new petrochemical processing units and supporting industrial infrastructure, highlighting the growing investment in downstream energy and chemical production.

Source: constructionreviewonline.com All rights reserved. Unauthorized reproduction prohibited.

Featured Companies

Comments

Leave a Reply

Your email address will not be published. Required fields are marked *