Statnett, Norway’s grid operator, is putting a hold on any additional power hookups being set aside for data centers. This move is expected to give the country ample time to decide how to manage the strain those facilities put on the grid, according to Bloomberg.
When will the Pause End?
According to a statement issued by Statnett on Monday, they will end the pause by Aug. 1, 2027, at the latest, according to Bloomberg.
“We want data centers in Norway, but we can’t have all types of data centers,” Digitalization Minister Torgeir Micaelsen told reporters on Monday, according to Bloomberg. “We must therefore control the growth and ensure that Norway gets the data centers we actually need, those that provide the greatest societal benefit,” Micaelsen said.

Statnett Issues Statistics on Data Centers Connection to the Grid
Statnett data show that data centers drawing 800 megawatts are already linked up, 4,200 MW has been set aside for them, and 9,100 MW more is waiting in line for capacity, according to Bloomberg. Additionally, requests for 18,000 MW more have also been made. Maximum power consumption in Norway is just over 25,000 MW.
Furthermore, according to Bloomberg, a report from the Norwegian Board of Technology, once construction wraps up, data centers will create few lasting jobs. The report also says foreign companies own 90% of data centers.
Global Data Centre Boom
Worldwide, data center construction has picked up speed. Currently, technology companies are investing hundreds of billions of dollars into the infrastructure needed to train and run artificial intelligence, according to Bloomberg. The pace has angered residents across the U.S. and Europe, who worry about the land the facilities occupy, the electricity they consume and rising power bills.
Data center projects in Norway have faced setbacks of their own. British AI infrastructure company Nscale is constructing its Glomfjord data center six months behind schedule and is also building another one in Narvik. The site, built for ByteDance, the owner of TikTok, has 6.4 MW running out of 30 MW planned.
Overview: Statnett Data Center Grid Connection Pause
Policy Action: Suspension of new high-voltage grid reservations and allocations for data center developments.
Enforcing Agency: Statnett (Norway’s national transmission system operator).
Impact Loop
Effective Duration: Active immediately, scheduled to run until August 1, 2027, at the latest.
Impact Loop
Core Goal: Give regulators breathing room to establish strict entry guidelines, prioritizing infrastructure with high societal value over low-benefit setups like crypto mining.
Grid Demand vs. Capacity
Norway Peak National Demand: 25,000 MW
Current Data Center Load: 800 MW
Impact Loop
Existing Reserved Capacity: 4,200 MW
Impact Loop
Active Queue for Connections: 9,100 MW
Impact Loop
Outstanding Inquiries: ~18,000 MW
Impact Loop
Total Combined Demand: Over 32,000 MW, exceeding the nation’s entire maximum grid usage.
Economic and Social Context
- Foreign Ownership: 90% of Norwegian data centers are foreign-owned.
- Job Creation: Low long-term employment yield post-construction (per the Norwegian Board of Technology).
- Public Pushback: Rising local anxiety over industrial land takeovers, heavy power draw, and upward pressure on consumer electricity rates.
Featured Project Overview
- Project: Glomfjord Data Center
- Developer / End User: Nscale (UK) / Built for ByteDance (TikTok)
- Status: Operational at 6.4 MW of a planned 30 MW capacity; currently 6 months behind schedule.