Project Factsheet: Steel River Energy Center
ProjectSteel River Energy Center (DC-coupled solar-plus-storage)
LocationWilson, Mississippi County, Arkansas, USA
Owner / operator / developerCypress Creek Energy
OfftakerGoogle (power purchase agreement, Phases 1 and 2)
Phases 1 & 21.6 GWdc solar and 1.9 GWh battery storage
Full buildout2.5 GWdc solar and 2.9 GWh battery storage by 2029 (three phases)
Homes poweredMore than 315,000 Arkansas homes a year
Financing$3.5 billion (secured June 2026)
Construction startJuly 2026
EPC contractorMoss
Structural steel159,000 tons domestic steel (~2.5x the Empire State Building); 400,000+ piles from PACO Steel (Blytheville) using 142,000+ tons of coil from U.S. Steel’s Big River Steel (Osceola)
Solar modulesFirst Solar (100% U.S.-made)
TrackersNextpower
Battery storageLG Energy Solution Vertech (U.S.-assembled, North American cells)
Jobs~700 construction jobs per phase
Tax revenue~$300 million over project life
Community investment$8 million combined (Google $5m; Cypress Creek $3m, including $400,000 for a Rivercrest School District playground)