Project Fact Sheet for Taweelah C Power Plant
Project: Taweelah C Independent Power Plant (IPP)
Location: Al Taweelah Power and Desalination Complex, Abu Dhabi, UAE
Project type: Combined-cycle gas turbine power plant
Capacity: 2.6GW
Project value: AED7.76 billion (US$2.1 billion)
Developer: TAQA (60%); Aljomaih Energy and Water Company and Sembcorp Industries (40% collectively)
Offtaker: Emirates Water and Electricity Company (EWEC)
EPC contractor: China Energy Engineering Corporation (Energy China)
Power generation technology supplier: Siemens Energy
Financing: Consortium of local and international banks
Financial close: November 2026
Expected commercial operation: 2029
Taweelah C Power Plant Project Team
TAQA: Majority shareholder and project developer
Aljomaih Energy and Water Company: Consortium partner and project investor
Sembcorp Industries: Consortium partner and project investor
Emirates Water and Electricity Company (EWEC): Electricity offtaker
China Energy Engineering Corporation (Energy China): EPC contractor
Siemens Energy: Gas turbines, steam turbines, generators and associated power technology
HSBC: Project financing lender
DBS: Project financing lender
OCBC: Project financing lender
KfW IPEX-Bank: Project financing lender
ICBC: Project financing lender
First Abu Dhabi Bank: Project financing lender
Abu Dhabi Islamic Bank: Financing arranger
Dubai Islamic Bank:Financing arranger