Construction crews are in a three-month sprint to complete the first four miles of the Mon-Fayette Expressway extension before its scheduled 20 November opening. The section now nearing completion — Sections 53A1 and 53A2, running from Jefferson Boulevard to Camp Hollow Road near West Mifflin — carries a cost of $380 million. It forms part of the wider Route 51-to-Duquesne corridor, which is estimated at $1.3 billion overall.
In an update provided to Construction Review Online, the Pennsylvania Turnpike Commission confirmed the section details and cost, noting that the $1.3 billion figure applies to the full Route 51–Duquesne corridor rather than the section opening in November. Remaining work on the section includes completing lane paving, finishing the bridge approach pavement — one of the last major items needed for opening — and testing the overhead toll gantries.
In 2023, the Pennsylvania Turnpike awarded Trumbull Corp. the first three contracts on the Mon-Fayette Expressway extension. Despite near-record rainfall in August, there is still significant work to complete over the coming months, project manager John Dzurko said. Another major road project advancing is the Midtown Bus Terminal redevelopment project in New York, a transportation infrastructure project intended to replace and expand the existing Midtown Bus Terminal and improve bus operations in the area.
Tutor Perini Corporation last year secured a $1.871 billion contract to construct the Staging and Storage Facility and Ramp Structure components of the programme. The contract was approved by the Board of Commissioners of the Port Authority of New York and New Jersey, which is overseeing the redevelopment.
Outlook on the Mon-Fayette Expressway Extension Project
The Mon-Fayette Expressway project involved a tremendous amount of earth moving, with roughly four million cubic yards of excavation through Jefferson Hills and West Mifflin. In particular, the first four miles required 11 bridges, 19.6 million pounds of steel and 59,531 cubic yards of concrete. In addition, crews had to coordinate a quick response to a landslide on nearby New England Road last month. Where the Mon-Fayette Expressway meets Route 885 near Allegheny County Airport, Trumbull built a new bridge along SR 885 to span the new highway. Contractors have not experienced major construction issues and have been able to keep to schedule despite the difficulties.
Expressway Completes 60-Year Regional Development Vision
Since the 1960s, community leaders in the Monongahela Valley have been working to stabilize the struggling steel industry by pursuing the Mon-Fayette Expressway. In particular, the first section was opened in 2002 at Route 51 in Jefferson Hills, and the remaining 58 miles were finished by 2012. The final stretch to Duquesne, however, has faced funding challenges. Robert Johnson, director of the Mon-Yough Area Chamber of Commerce, is bullish on the Mon-Fayette Expressway project. Moreover, he thinks it played a role in Nippon Steel’s decision to spend billions of dollars on keeping valley facilities.

Construction crews are in a three-month sprint to complete the first four miles of the Mon-Fayette Expressway extension
Project Overview
- Project Name: Mon-Fayette Expressway Extension, Sections 53A1 and 53A2
- Section Value: $380 million (Sections 53A1 and 53A2, opening November 2026)
- Wider Corridor Value: $1.3 billion estimate (Route 51 to Duquesne)
- Location: Jefferson Boulevard to Camp Hollow Road, near West Mifflin, Pennsylvania
- Primary Contractor: Trumbull Corp. (first three contracts)
- Status: First four miles opening November 20, 2026
Scope
- 11 bridges across the first four miles
- Overhead license plate toll gantry system
- New SR 885 bridge spanning the new highway near Allegheny County Airport
- Approximately four million cubic yards of excavation
- Bridge approach pavement (among the last major items before opening)
Project Highlights
- Culminates a 60-year regional pursuit dating to the 1960s
- 19.6 million pounds of steel in the first four miles
- 59,531 cubic yards of concrete required
- Provides alternate airport access for eastern suburbs
Key Developments
- Construction began early 2023
- First four-mile section (53A1 and 53A2) opening November 20, 2026
- Second segment (West Mifflin to Dravosburg) began January 2026
- $163.6 million section to Dravosburg targeted for 2029
- Route 837 bridge replacement planned to advertise late 2026
Key Challenges
- Near-record August 2026 rainfall impacted construction but did not delay the project
- August landslide on adjacent New England Road
- Turnpike Commission funding constraints for final sections
- Oil Franchise Tax revenue declined from $150M to $120M annually
Outlook
- First four miles open November 20, 2026
- West Mifflin to Dravosburg section completion 2029
- Final design work pending legislative funding authorization
- Route 837 corridor to Kennywood Park awaiting funds
- Northern Duquesne–Monroeville section not anticipated until late 2030s