Construction of two renewable energy projects in Spain begins

Home » News » Construction of two renewable energy projects in Spain begins

Construction of two renewable energy projects by Enel green power in Spain has begun. The projects include: The Los Naranjos photovoltaic (PV) plant in the community of Andalusia, and the Los Gigantes wind farm in the community of Aragon.

Solar power plant in Andalusia

In the autonomous community of Andalusia, Enel Green Power has started construction on its second photovoltaic (PV) plant of around 50MW in the town of Carmona, Seville province. The construction of this PV plant, known as “Los Naranjos”, to be completed by the end of 2020, will involve an investment of 28.2 million euros.

Los Naranjos will be composed of 128,520 PV panels of 340Wp each. To operate the facilities, EGP, will build 9 switching stations, an electric substation and an underground cable network spanning 4.5km. This facility, once operational, is set to produce about 100GWh a year, hence avoiding the emission of approximately 67,000 tons of CO2 into the atmosphere each year.

Since the end of 2019, EGP has been building another 50 MW “Las Corchas” PV plant in Carmona. These two facilities are the company’s biggest PV plant developed in Andalusia to date, with a combined capacity of around 100MW.

These plants will be built under sustainable engineering criteria, whereby Enel Green Power’s “Sustainable Construction Site” model will be applied. This model envisages the installation of PV panels to meet some of the energy needs during the construction works and water saving measures by installing deposits and rain collection systems. Once the works have been completed, both the PV panels and the water saving equipment will be donated to the town for public use. These initiatives have been included as sustainable engineering actions as part of the 2018 Climate Projects by Spain’s Ministry of Ecological Transition (MITECO).

Also Read: Construction of 50MW PV plant in Carmona, Spain begins

Wind farm in Aragon

In the autonomous community of Aragon, construction of “Los Gigantes”, a new 21.3 MW wind farm in the towns of Blesa and Moyuela in the Teruel and Zaragoza provinces has begun. Investment in this project amounts to US $21.6m.

The wind farm, which will comprise six wind turbines of 3.55MW each, will generate around 62GWh of power per year once they come online, which is expected before the end of the year. Once fully operational, this facility is set to avoid the emission of approximately 41,000 tons of CO2 into the atmosphere.

In 2019, Enel Green Power España connected three wind farms in Aragón located in the Teruel and Zaragoza provinces, for a total capacity of 424 MW.

EGP employs a project development model that encompasses actions to create social value for the areas in which they are built, the so-called Creating Shared Value (CSV) model. For these four projects, the CSV actions have prioritized the incorporation of local labor, as well as locally hiring catering services and workers’ accommodation.