The Kuwait Dorra Gas Field project is advancing through its main procurement phase, with international engineering contractors competing for a major construction opportunity near the Al-Zour refinery.
State-owned Kuwait Gulf Oil Company (KGOC) tendered the estimated $3.3 billion onshore facility in August 2026. The development will process natural gas and condensates from the offshore Dorra field in the Saudi-Kuwait Neutral Zone.
Consequently, the project represents a significant investment in Kuwait’s energy infrastructure and domestic gas-processing capacity. The contract could also become the country’s largest oil and gas sector award in more than a decade.
The procurement process follows several months of delays linked to regional security concerns and shipping disruptions. However, KGOC resumed the tender process after earlier uncertainty had placed the project on hold.
The current bid deadline is December 29, 2026, while the contractor engagement meeting was rescheduled from September 14 to October 14. Earlier meetings attracted representatives from seven international engineering companies, although the latest reported meeting arrangements require careful distinction from previous attendance figures.
Dorra Gas Field Targets Major Capacity
The proposed facility will process up to 632 million cubic feet of gas daily, alongside approximately 60,000 barrels of condensates per day. These products will arrive through infrastructure connected to the offshore Dorra field development. The plant will occupy a site beside the Al-Zour refinery, creating opportunities to integrate processing operations with Kuwait’s existing energy infrastructure.
KGOC has allocated approximately 700,000 square meters for the development. The site preparation scope includes work that may require backfilling, shoring and dewatering. Local contractor Ahmadiah Contracting & Trading Company secured the site preparation contract in August 2026, marking a tangible construction milestone ahead of the main plant works.
Meanwhile, Technip Energies completed the project’s front-end engineering and design work. The main engineering, procurement and construction contract will cover delivery of the processing facility and its associated systems. KGOC has also planned specialist technology packages for acid gas removal and sulphur recovery. Honeywell UOP and Shell Catalysts & Technologies have been identified as intended technology providers for those units.
The Kuwait Dorra Gas Field project and Qatar’s $40 billion North Field West Offshore Expansion highlight the Gulf’s growing investment in gas infrastructure. While the Dorra-linked facility is designed to process up to 632 million cubic feet of gas daily and 60,000 barrels of condensate, North Field West will add 16 million tonnes per annum of LNG capacity through two new processing trains. Both developments require extensive engineering, procurement and construction work to connect offshore gas resources with onshore processing facilities.
Dorra Gas Field Draws International Contractors
Seven international engineering companies had expressed interest in the tender by February 2026. They include Samsung E&A, Larsen & Toubro, Técnicas Reunidas, Saipem, Hyundai Engineering & Construction, Hyundai Engineering Company and JGC. Their previous participation in contractor meetings demonstrates strong international interest in Kuwait’s energy construction market. However, attendance at earlier meetings does not establish which companies will submit final bids.
KGOC is using a fast-track tender process that excludes Kuwait’s Central Agency for Public Tenders (CAPT). Ordinarily, CAPT reviews technical and commercial bid evaluations and checks whether procurement remains competitive. Removing that approval stage could shorten the procurement timetable. Nevertheless, contractors must still assess technical requirements, project risks and commercial conditions before submitting proposals.
Regional security remains a significant concern because the offshore Dorra field lies in a disputed maritime area. Iran refers to the field as Arash and claims that part of it extends into Iranian territory. These competing claims could complicate offshore operations and infrastructure security. Furthermore, disruption around the Strait of Hormuz has previously delayed project procurement and affected shipping routes.
KGOC faces the challenge of progressing a major energy project while managing these geopolitical and logistical risks. The December 29 bid deadline remains the next key procurement milestone. A successful tender process would move the development closer to construction of a major gas-processing facility serving Kuwait’s wider energy system.

Also read: $8bn Bab Gas Cap Project: UAE Gas Plant EPC Bid Race Widens Attracting Four Major Consortiums
Project Fact Sheet
Name: Dorra Gas Processing Project, also described as the Kuwait onshore gas processing facility.
Location: Near the Al-Zour refinery, Kuwait.
Estimated construction value: $3.3 billion.
Owner and developer: Kuwait Gulf Oil Company (KGOC).
Parent organisation: Kuwait Petroleum Corporation (KPC).
Type: Onshore natural gas and condensate processing facility.
Planned gas-processing capacity: Up to 632 million cubic feet per day.
Planned condensate-processing capacity: Approximately 60,000 barrels per day, according to the August 2026 tender report.
Site area: Approximately 700,000 square metres.
Feedstock source: Offshore Dorra field in the Saudi-Kuwait Neutral Zone.
Procurement model: Fast-track engineering, procurement and construction (EPC) tender.
Bid submission deadline: December 29, 2026.
Site preparation contractor: Ahmadiah Contracting & Trading Company.
Front-end engineering and design contractor: Technip Energies.
Planned specialist systems: Acid gas removal and sulphur recovery.
Project status: Main EPC tender issued in August 2026; final contractor selection remains unconfirmed in the cited reports.
Project Team
Owner and developer: Kuwait Gulf Oil Company (KGOC).
Parent Energy Corporation: Kuwait Petroleum Corporation (KPC).
Site preparation contractor: Ahmadiah Contracting & Trading Company.
Front-end engineering and design contractor: Technip Energies.
Prospective EPC contractors:
- Samsung E&A
- Larsen & Toubro
- Técnicas Reunidas
- Saipem
- Hyundai Engineering & Construction
- Hyundai Engineering Company and JGC
Planned acid gas removal technology provider: Honeywell UOP.
Planned Sulphur recovery technology provider: Shell Catalysts & Technologies.
Offshore field development operator: Al-Khafji Joint Operations (KJO).
Offshore development partners: Aramco Gulf Operations Company and Kuwait Gulf Oil Company, through their respective parent organizations.
Adjacent refinery operator: Kuwait Integrated Petroleum Industries Company (KIPIC)