Project Blue: $3.6bn Tucson Data Center Construction Advances in Arizona Amid Power Dispute

Home » Buildings » Data Center » Project Blue: $3.6bn Tucson Data Center Construction Advances in Arizona Amid Power Dispute
A data center

Project Blue construction is advancing in Pima County, Arizona, as Beale Infrastructure pursues a $3.6 billion hyper scale campus. The development occupies approximately 290 acres near the Pima County Fairgrounds, southeast of Tucson. It will accommodate up to 10 data center buildings, creating a major addition to the region’s digital infrastructure. However, the project faces continuing regulatory scrutiny over electricity supply, environmental commitments and community concerns.

The development initially attracted attention after Pima County approved the project in June 2025. Subsequently, the City of Tucson rejected the proposed annexation in August 2025. This decision forced developers to reconsider the original water supply and cooling arrangements.

Nevertheless, Beale Infrastructure continued pursuing the development outside Tucson’s municipal boundaries. Pima County confirmed that the land transaction closed on December 24, 2025, generating approximately $20.85 million. Construction activity subsequently began in April 2026.

Project Blue Construction Advances Following Site Acquisition

The project occupies land within Pima County’s Southeast Employment and Logistics Center. Its proposed development includes up to 10 buildings covering approximately 2.25 million square feet.

The investment comprises approximately $1.2 billion in construction expenditure and $2.4 billion in equipment. Consequently, the project represents one of Southern Arizona’s largest proposed private infrastructure investments.

Beale Infrastructure leads development through its associated project entities. Meanwhile, Humphrey’s Peak Properties LLC holds the development interests associated with the land transaction.

Site preparation commenced in April 2026, although building approvals remain an important milestone. Pima County permit records reviewed in November identified building and foundation applications submitted on October 19, 2026. Both applications carried a Request for Corrections status.

Therefore, the project has progressed beyond planning and land acquisition, but the available records do not establish completed building construction. The first facility could become operational in 2027, while developers target full campus operations by 2028.

Project Blue Revises Cooling and Electricity Infrastructure Plans

The development’s infrastructure strategy changed significantly after Tucson rejected annexation. Initially, developers proposed an 18-mile reclaimed water pipeline and a 30-acre aquifer recharge facility.

However, Beale subsequently adopted an air-cooled, closed-loop cooling system. This arrangement reduces dependence on municipal water infrastructure and changes the project’s original environmental management strategy.

Electricity supply remains another major component. In December 2025, the Arizona Corporation Commission approved a 10-year electricity supply agreement involving Tucson Electric Power (TEP) and Humphrey’s Peak Power.

The agreement supports electricity provision for the development. Furthermore, the utility’s infrastructure arrangements require the customer to pre-fund project-related construction costs.

The Arizona Attorney General challenged the electricity agreement in February 2026. Attorney General Kris Mayes argued that its rate-setting provisions undermine the Corporation Commission’s constitutional authority.

The City of Tucson also challenged the agreement. On October 1, 2026, the Superior Court rejected motions seeking dismissal and ordered further arguments on the case’s merits.

Consequently, the electricity arrangement remains subject to litigation. Nevertheless, the regulatory dispute has not automatically halted the ongoing development activities.

Project Blue Faces Wider Data Infrastructure Scrutiny

The development illustrates the growing challenges surrounding hyper scale construction in electricity-constrained communities. In September 2026, Pima County approved a 120-day moratorium on new data center applications in unincorporated areas.

However, the restrictions exempted Project Blue because development activity had already commenced.

The project also faces scrutiny over construction impacts, water consumption and electricity costs. In May 2026, county authorities cited the site’s contractor over dust-control violations.

These concerns demonstrate why large data center developments increasingly require detailed infrastructure and environmental planning.

Elsewhere, Wyoming is advancing another major hyper scale development involving Microsoft’s three planned facilities. Cheyenne Light has signed agreements covering electricity distribution and transmission infrastructure for those developments.

The Microsoft data center buildout in Wyoming provides another example of how developers and utilities are addressing the infrastructure requirements of hyper scale computing. Both developments highlight the importance of dedicated electricity infrastructure, customer-funded improvements and regulatory coordination in large-scale data center construction.

Project Blue

Updated December 3, 2025: 

Amazon has pulled out of the embattled Project Blue data center according to latest insight. This was relayed by city and county leaders, however another large company may take over. Pima County Supervisor Matt Heinz and Tucson City Councilman Paul Cunningham noted their remarks. Heinz noted he heard rom multiple sources that Amazon will no longer be the end user. However, he confirms that there are now potentially seven or eight different end-user tenants. Developer Beale Infrastructure, which was set to lead the project to build the facility near the Pima County Fairgrounds, said Tuesday that while Amazon showed interest, it never had an agreement in place.

“AWS has previously engaged in standard due diligence processes in Arizona, like we do in any geographic location we consider building and operating our infrastructure,” Amazon noted in a statement. However, they noted they do not have any commitments or agreements in place to ensure their data center developments provide the best possible product and value. On the other hand, Beale said it cannot comment on the intentions of other companies. There has been strong opposition to Project Blue from the start, with most questioning the facility’s water and power use. In fact, Beale changed the plans for the facility from water-cooled to air-cooled, but the opposition remained. Beale later said it was committed to using renewable sources for the facility. Major companies such as Microsoft are making strides in their data center projects with their largest and most advanced project taking shape in Mount Pleasant, Wisconsin. 

August 7, 2025: TUCSON, Arizona – The Pima County Board of Supervisors has approved the rezoning and comprehensive plan amendments needed to pave the way for Project Blue, a $3.6 billion data center campus slated for Tucson’s Southeast Employment and Logistics Center (SELC) near the Pima County Fairgrounds. The vote passed narrowly at 3-2.

A Strategic Tech Investment

Project Blue, led by San Francisco-based Humphrey’s Peak Properties, LLC, and developed by Beale Infrastructure, will span 290 acres and is set to become one of the largest electricity consumers in the Tucson Electric Power (TEP) grid. The project will consist of up to 10 buildings totaling 2.5 million square feet upon full buildout.

Though the developers will not seek local economic incentives, they are leveraging state-level incentives to support the project. County Administrator Jan Lesher emphasized the project’s broad economic significance, calling data centers the “physical backbone of the internet.”

Economic and Environmental Commitments

The development is projected to create:

  • 180 permanent jobs by 2029 with an average salary of $64,000
  • 3,024 direct construction jobs
  • 2,049 indirect jobs during the 2026–2028 construction phase

The initial investment includes $1.2 billion in construction and $2.4 billion in new equipment, with a $63.5 million annual economic impact by 2029.

Project Blue Data Center is also committing to sustainable water use, planning to use 100% renewable reclaimed water. Developers will fund an 18-mile reclaimed water pipeline and a 30-acre aquifer recharge facility to replenish water lost to operations.

Also Read Data center construction boom 

Energy, Annexation, and the Road Ahead

A long-term energy agreement with TEP ensures Project Blue will become one of its biggest customers while supporting the utility’s clean energy goals, particularly in solar and energy storage.

Final approval hinges on the City of Tucson’s annexation of the land, which is essential for securing water service. If annexation fails, Pima County will retain ownership.

Construction is expected to begin in late 2025 or early 2026, with the first data halls operational by 2027.

Who Loses as Amazon Cancels Billion Dollar Data center Project in Becker, Minnesota?

Project Blue data center

Source: constructionreviewonline.com All rights reserved. Unauthorized reproduction prohibited.

Featured Companies

Comments

Leave a Reply

Your email address will not be published. Required fields are marked *