Project Fact Sheet
NameProject Blue Data Center.
LocationSoutheast Employment and Logistics Center, near Houghton Road and Pima County Fairgrounds, Pima County, Arizona, USA.
ValueApproximately $3.6 billion.
Construction investmentApproximately $1.2 billion.
Equipment investmentApproximately $2.4 billion.
Site areaApproximately 290 acres.
Planned developmentUp to 10 data center buildings.
Planned building areaApproximately 2.25 million square feet.
Initial construction activityApril 2026.
First operational facilityTargeted for 2027.
Full campus completionTargeted for 2028.
Cooling systemAir-cooled closed-loop system.
Electricity providerTucson Electric Power.
Electricity agreement10-year supply arrangement.
Land transactionClosed December 24, 2025.
Land transaction valueApproximately US$20.85 million.
Construction employmentMore than 3,000 direct jobs forecast.
Permanent employmentApproximately 180 positions.
Regulatory authorityArizona Corporation Commission.
Local planning authorityPima County.
Current challengesElectricity agreement litigation, environmental concerns and outstanding building permit reviews.
Project Team
DeveloperBeale Infrastructure.
Development entityHumphrey’s Peak Properties LLC.
Electricity providerTucson Electric Power.
Electricity regulatorArizona Corporation Commission.
Landowner before acquisitionPima County.
Local planning and permitting authorityPima County Development Services.
Legal oversightMaricopa County Superior Court.
State legal authorityArizona Attorney General’s Office.
Construction contractorAmes Construction (identified in reporting on site preparation).
Cooling infrastructureBeale Infrastructure.
Engineering consultantsNot publicly identified in the reviewed disclosures.
Architectural consultantsNot publicly identified in the reviewed disclosures.