Project Overview
- Project Value: $3 Billion+ (Estimated concessional financing)
- Location: Vakhsh River, Tajikistan
- Developer: Tajikistan Government & Webuild
- Status: Construction active; partial electricity generation underway
Scope
- 335-meter embankment dam construction
- 3,780 MW hydropower generation facility
- Complex reservoir filling operations
- Widespread community resettlement programs
Project Highlights
- Becomes the world’s absolute tallest embankment dam
- Eliminates Tajikistan’s chronic winter electricity shortages
- Exports massive hydropower to Kazakhstan and Uzbekistan
- Two generating units are already producing active electricity
Key Developments
- Parliament ratified a $300 million World Bank grant
- Total World Bank financing reached $650 million recently
- Italy committed $150 million via its Climate Fund
- Dam structure successfully reached 190 meters in August
Key Challenges
- Safely constructing the remaining 145 meters of height
- Managing downstream water concerns for Uzbekistan agriculture
- Addressing environmental criticisms over outdated climate data
- Monitoring complex gradual reservoir filling through 2039
Outlook
- Facility expected to be fully operational by 2033
- Will generate 14.4 billion kWh of power annually
- Concessional financing will reach up to $3 billion
- Hydropower will balance growing regional solar generation