Fact Sheet for TotalEnergies and Nextnorth 440 MW Solar Project in the Philippines
Project name440MWp Ilagan Solar Project
LocationIlagan City, Isabela Province
TechnologyUtility-scale solar PV
Capacity440MWp
Investment valueUS$300 million
DevelopersTotalEnergies, Nextnorth
Expected CODEnd-2027
Generation forecast13.5TWh over 20 years
OfftakeCorporate PPAs and national grid sales
FinanciersSMBC, ING, Standard Chartered

Project Timeline
Project awarded under GEAP Round 4Previously secured
Financial close achievedApril 2026
Construction startApril 2026
Major EPC mobilization2026
Peak construction phase2026-2027
Grid integration works2027
Commercial operations date (COD)End-2027
TotalEnergies and Nextnorth 440 MW Solar Project in the Philippines: Project Cost
Project valueUS$300 million
Ownership structure:
- TotalEnergies – 65%
- Nextnorth – 35%
Debt financiers:
- Sumitomo Mitsui Banking Corporation (SMBC)
- ING Bank NV
- Standard Chartered Bank
Revenue structure:
- 50% under long-term PPAs with AdventEnergy and PrimeRES
- Balance sold into national grid under Green Energy Auction Program Round 4
This financing structure substantially de-risks merchant exposure while ensuring a stable revenue base during the project’s early operating years.
Project Team
Developers
- Lead international developer: TotalEnergies
- Local development partner: Nextnorth
Financing institutions
- SMBC
- ING Bank
- Standard Chartered
Offtakers / Retail Electricity Suppliers
- AdventEnergy
- PrimeRES
Government framework
- Philippines Department of Energy
- Green Energy Auction Program (GEAP Round 4)