Squadron Energy has lodged a scoping report for the proposed A$1.5 Bn (US $980 Mn) Cullen Bullen Battery Storage (BESS) project near Lithgow in New South Wales, Australia. The project is planned to deliver up to 1,000MW of power and 8,000MWh of storage, equivalent to eight hours at full output. If developed as proposed, it would rank among Australia’s largest grid-scale battery projects. Similarly, the proposed development adds to Australia’s expanding battery storage sector, following the commencement of Stage 1 operations at Quinbrook’s Supernode Battery Energy Storage Project in Queensland.
The proposed facility would occupy approximately 660 hectares of previously cleared grazing land at Hillcroft, 141 Red Springs Road, Cullen Bullen, around 25 kilometres north of Lithgow and 130 kilometres north-west of Sydney. Squadron Energy is investigating a connection to an existing 500kV transmission line. The company is targeting construction commencement in 2030, subject to planning approvals, project development and investment decisions.
Project scope and grid connection
The proposed battery is intended to store electricity when generation is high and discharge it when demand increases. Its eight-hour storage duration would provide longer-duration flexibility than many shorter-duration battery installations.
According to the project scoping information, the system would also provide voltage control and support grid stability and inertia. This would help balance fluctuations in renewable generation and strengthen the integration of wind and solar power into Australia’s National Electricity Market. The proposed connection to the existing 500kV transmission infrastructure is intended to support the transfer of stored electricity into the wider grid.
Site development and community engagement
Thev Cullen Bullen BESS project is proposed beside the former Cullen Valley coal mine, in a region undergoing a transition from coal-based electricity generation towards renewable energy and storage. The surrounding area is also attracting other proposed wind and battery developments, making transmission access and coordination with regional energy infrastructure important considerations.
Squadron Energy has indicated that it intends to enter into a voluntary planning agreement with Lithgow City Council. Its proposed community benefit-sharing contribution is based on A$150 per MWh per annum under the applicable NSW guidelines, with part of the benefit intended to support Cullen Bullen and nearby communities. The company has also highlighted opportunities for local employment, training, infrastructure investment and community programmes.
Project status and next steps
The filing of the scoping report marks an early planning milestone. It does not constitute final development approval or a final investment decision. Further environmental assessment, planning requirements, grid connection arrangements and investment approvals will be needed before construction can proceed.
Squadron Energy’s current target is to begin construction in 2030. The proposed 1,000MW/8,000MWh capacity and A$1.5 billion project value remain development estimates and may change as the design and approval process advances.