Fact Sheet for Alphabet’s Northern Indiana Data Center Power Supply Deal
End UserAlphabet Inc. through its subsidiary
Utility PartnerNiSource Inc.
Energy Delivery EntityNIPSCO Generation LLC (GenCo)
Power Capacity340MW plus up to 175MW additional supply
Energy ModelDedicated GenCo portfolio
Start of SupplySummer 2026
Key FeatureUtility-backed, large-load energy structuring
The agreement also comes alongside expanded energy arrangements between NiSource and Amazon. This is as the American multinational tech company continues to advance construction at various sites in the US, including its landmark $ 10 billion data center in Richmond County, North Carolina.