Project Fact Sheet
NameMonarch Compute Campus
TypeArtificial intelligence data center campus
LocationMason County, West Virginia, United States
DeveloperNscale
Site areaMore than 2,250 acres
Anthropic capacityApproximately 460MW
Anthropic agreement valueApproximately $45 billion
Agreement durationSix years
Phase 1 AI computing capacity1.35GW
Potential future capacityMore than 8GW
Planned onsite power capacity2GW
Power sourceNatural gas generation
Reported overall development costApproximately $69 billion
Nscale planned capital investmentMore than $20 billion
AI processor technologyNvidia Vera Rubin
Expected Vera Rubin deploymentLate 2027
Phase 1 delivery targetEarly 2028
Power infrastructureState-certified AI microgrid
Grid connectionIndependent onsite generation
Cooling technologyClosed-loop cooling
Microsoft capacity arrangementUp to 1.35GW
Microsoft deployment technologyNvidia Vera Rubin NVL72
Employment projection2,090 jobs
Projected annual Mason County GDP contribution$395 million
Campus expansion strategyMulti-phase development exceeding 8GW
Current statusUnder development
Project Team
DeveloperNscale
Data center operatorNscale
Project ownerNscale
Previous project sponsorFidelis New Energy
Previous investment sponsor8090 Industries
Acquired project entityAmerican Intelligence & Power Corporation
AI technology partnerNvidia
GPU technology providerNvidia
Power generation partnerCaterpillar
Anthropic computing customerAnthropic
Microsoft computing customerMicrosoft