Construction of the $3 billion Google Botetourt County data center has been temporarily suspended by a judge. The Botetourt County Circuit Court decision came Monday evening and overturns a major contract that was scheduled to expire in June 2025. In addition, resident Robert Dallas filed a lawsuit against the county and a Google shell company. His suit argued the June 2025 approval skipped Virginia’s Freedom of Information Act steps. In the meantime, some residents are celebrating the court victory at the Botetourt Center at Greenfield.
The decision has three immediate implications. It invalidates the contract, suspends construction and cancels any actions taken after the June 2025 meeting. Moreover, it is a challenge for both sides, as money has already been paid and construction has already begun. “FOIA does matter and we demonstrated that. There is a need for transparency with the county.” said one of the celebrating residents.
Other Projects
The $10 billion Project Delta data center agreement took shape as Stokes County officials approved the project. The Engineered Land Solutions proposal, which covers over 1,800 acres, passed the commissioners’ vote 3-2 on Tuesday. In addition, the site encompasses four tax parcels adjacent to Walnut Cove and the Dan River. The vote came after a public hearing on Nov. 9 and a last-week update to the agreement. The agreement, meanwhile, sets the rules of the property for 15 years. In addition, it provides a more direct route to a project that could significantly increase the tax base, commissioners say. Besides, it offers many lucrative employment opportunities in addition to those financial benefits.
Scope of the Google Botetourt County data center
The campus is a certified giant. In June 2025, Google purchased a 312-acre site at the Greenfield industrial park for $14 million. In addition, state permit applications reveal three data center buildings, with a combined area of approximately 921,000 square feet. Both are approximately 300,000 square feet in size, with plans for three substations, an office building and site works. Moreover, the county performance agreement requires at least $3 billion in investment. It also requires at least 150 workers with a median salary of at least $86,000. Furthermore, those terms tie to a first-building completion by 2030. Google also pledged $4 million for community projects.
At the heart of that buildout is the voided contract. Dallas sued the county and Google’s shell company over the June 2025 approval. The court ruled the process was in violation of the state’s open-meetings law. The judge thus set aside that approval, placed a hold on the property and cancelled the county’s later actions. Another supporter said Dallas “basically gave Google a black eye. He hit a giant in the face and knocked him down.
Outlook for the halted data center construction
The county is now considering its legal options. County officials said the county is “carefully considering” the ruling with its legal counsel. Minimal construction activity will be done during the holidays to ensure this site is in compliance with permits. So crews will be doing only stabilization work, while lawyers work out the way forward.
The cure path, according to project opponents, is a procedural one. One opponent said that all the county has to do is hold another public hearing and approve that contract. In addition, opposition groups are preparing more activity in the near future. I believe in the next three or four weeks, you will see a lot of things emerge from the groups that opposed this,” the same voice continued. “We want the people’s voice to be heard.”
Google responded late Tuesday afternoon. The company said in a statement that it is “evaluating yesterday’s ruling by the court. In addition, Google stated it is “committed to working transparently with Botetourt County and the community in full compliance with all legal and regulatory requirements. Finally, the timeline has shifted to the holidays, with little site work going on, the county deciding on an appeal or rehearing, and Google considering its challenge. Next, the $3 billion campus is on track or off track based on the 2030 first-building gate.