Project Factsheet: Hartsfield-Jackson Terminal Fire-Safety Upgrades
- Project: Central Passenger Terminal Complex Fire and Life Safety Enhancement Program
- Location: Hartsfield-Jackson Atlanta International Airport, Atlanta, Georgia
- Owner: City of Atlanta, Department of Aviation
- Approving authority: Atlanta City Council
- Council action: November 2, 2026
- Latest construction allocation: $36.84 million for Concourse B
- Current broader contract ceiling: Approximately $108.84 million
- Earlier funded phases: Pedestrian-mall level and Concourse A
- Next identified phase: Concourse C, subject to a future funding request
- Construction contractor: NSMS joint venture
- Contract partners: New South Construction, McCarthy Building Companies and Synergy Development Partners
- Delivery model: Construction manager at risk
- Concourse B detailed construction scope: Not publicly itemized in the records reviewed
- Concourse B construction schedule: Not publicly disclosed