US-based Jacobs Lands DFW Skylink Modifications Role on $4 Billion Terminal F Expansion

Home » Transport » Airports » US-based Jacobs Lands DFW Skylink Modifications Role on $4 Billion Terminal F Expansion

Jacobs has landed the DFW Skylink modifications role on the airport’s $4 billion Terminal F expansion. The firm was chosen Nov. 24 by Dallas-Fort Worth International Airport. In addition, the assignment designs structural changes to the elevated Skylink people-mover guideway. The design allows two parallel taxi lanes for aircraft to pass under the rail system at Dallas-Fort Worth International Airport. Jacobs’ other design contract value and construction timeline are not disclosed.

Nevertheless, the engineering challenge is the work to be done. Engineers need to modify existing spans of the Skylink bridge without disrupting the automated rail system. In addition, Jacobs will work with the Innovation Next+ design-build joint venture to sequence construction. Furthermore, the work includes the structural changes between the expanded terminal and DFW’s taxiway system. This means that the guideway remains operational while aircraft pass underneath.

Other Projects

Austin-Bergstrom International Airport (AUS) reached a pivotal milestone with the approval of a new Airline Use and Lease Agreement (ULA), effectively unlocking approximately $5 billion in funding for the most significant expansion in the airport’s history. This agreement, finalized between the City of Austin and its major carrier partners—including Southwest, American, and Delta—sets the financial and operational framework for the “Journey With AUS” program.

Scope of the Jacobs DFW Skylink Modifications

Moreover, the development of Terminal F changed the assignment. The terminal was originally designed as a 15-gate domestic terminal. Since then, it has grown into a 31-gate complex handling international flights and widebody aircraft. That expansion requires new airfield connections under the elevated rail line, not the movement of the system. Furthermore, the strategy maintains the modular design that was used in the design of the terminal from the beginning.

The money picture is a two-track operation. The joint venture’s ceiling was increased by $300 million in April, according to airport board records. In addition, that lift pushed the design-build contract up to about $2.06 billion for Terminal F and the Skylink Station. That ceiling is also well above the $855 million award in 2024. The original scope was for a 400,000 square foot concourse and Skylink station. In the meantime, Jacobs’ design contract has no known value. Also, costs that have not been agreed upon are charged on a time and materials basis until they are finalized.

“Thoughtful phasing, practical design and creative engineering that keeps people and commerce moving is no small task to keep Skylink running throughout construction,” Jacobs Executive Vice President Tom Meinhart said in a statement.

Outlook for the Terminal F construction programme

The buildout of the station shows the sequencing at work. On Nov. 3, DFW said it had hoisted all six prefabricated Skylink station modules into place on the existing rail system. Furthermore, each module weighed between 210 and 310 tons and each lift lasted about 8 hours in controlled overnight operations. In the meantime, the temporary service changes closed a stretch of track overnight, but kept all stations open.

However, the schedule has known movement. The ceiling on the joint venture was raised by $582 million in a January board action. It also added 379 days to the completion time. Then, the April authorization kept the Aug. 29, 2028 contract completion date, but that doesn’t mean all 31 gates open at that time. In total, DFW will open the first 15 gates in 2027, with the remaining 16 gates to be opened in future phases. Then, Terminal F delivers 31 American Airlines-served gates, expanded international processing and a Terminal D pedestrian link. As a result, everything comes down under a never-ending Skylink.

Jacobs DFW Skylink modifications

Source: constructionreviewonline.com All rights reserved. Unauthorized reproduction prohibited.

Featured Companies

Comments

Leave a Reply

Your email address will not be published. Required fields are marked *