$130 Million Victoria Inland Rail Project: John Holland Advances Tranche 2 Construction

Home » Transport » Rail » $130 Million Victoria Inland Rail Project: John Holland Advances Tranche 2 Construction

Victoria Inland Rail project is advancing its second construction tranche as Australia continues upgrading the Beveridge-Albury freight corridor. The project originally received an approximately A$200 million contract for its first construction tranche.

That value equates to about $130 million based on the exchange rate around the 2022 contract award. McConnell Dowell delivered that first tranche across four sites. Construction has since moved into Tranche 2 under John Holland.

The Victorian section forms part of Australia’s Inland Rail program. It upgrades 262km of existing railway between Beveridge and Albury-Wodonga. The works will provide the clearance needed for double-stacked freight trains.

Victoria Inland Rail project completes first tranche

McConnell Dowell completed Tranche 1 construction across Wangaratta, Glenrowan, Barnawartha North and Seymour. The works included bridge replacements, station modifications and track lowering.

At Wangaratta, the contractor transformed the station precinct and replaced the adjacent Green Street Bridge. The works also relocated tracks, added a western platform and replaced two footbridges with a pedestrian underpass.

At Barnawartha North, crews lowered the track beneath the Murray Valley Highway. They also replaced the Beaconsfield Parade Bridge at Glenrowan. At Seymour, the project replaced the Seymour-Avenel Road Bridge.

The first tranche created significant local economic activity during construction. Almost 1,650 people worked on the project, including apprentices, young workers and First Nations employees. Local businesses secured contracts worth A$161.3 million.

Victoria Inland Rail project enters second construction tranche

John Holland is now delivering Tranche 2 across eight sites between Benalla and Wandong. The works include station modifications, bridge replacements and track lowering.

Construction is underway at Benalla, Euroa, Seymour, Tallarook, Broadford and Wandong. The program includes modifications at Benalla Station and a vehicle underpass at Euroa.

Crews are also lowering track near the Hume Freeway at Seymour and Tallarook. At Wandong, construction includes bridge replacement works. Broadford has three work areas covering bridge replacement and track-lowering activities.

In September 2026, Inland Rail removed the Marchbanks Road Bridge at Broadford during an 86-hour rail possession. John Holland installed four new girders weighing 600 tonnes combined. The replacement bridge will stand 3.7 meters higher and 11 meters wider than the existing structure.

The Marchbanks Road works marked the ninth and final bridge replacement required across the Beveridge-Albury section. Inland Rail has now achieved the necessary double-stack clearance at 11 of its 12 sites. Tallarook remains the final location requiring modifications.

Victoria Inland Rail project strengthens Australia’s freight network

The completed and ongoing works will allow double-stacked freight trains to operate between Beveridge and Albury. The Victorian section connects with the broader Inland Rail route extending through New South Wales and Queensland.

The Australian Government confirmed in May 2026 that Inland Rail will be delivered between Beveridge and Parkes by the end of 2027. This will support double-stacked freight movements between Melbourne, Perth and Adelaide through Parkes.

The Victorian construction program also sits alongside Australia’s expanding passenger rail pipeline. The Newcastle-Sydney High Speed Rail project is progressing its Development Phase, including advanced manufacturing and major tunneling packages.

The two programs highlight Australia’s continuing investment in rail construction capacity. While Inland Rail focuses on freight efficiency, Newcastle-Sydney High Speed Rail is preparing infrastructure for high-speed passenger services.

The Newcastle-Sydney project has entered a A$659.6 million Development Phase. Its proposed railway will support journeys between Newcastle and Sydney in about one hour.

Also Read: Bidders for Australia’s North East Link project officially selected

Remarks on the Victoria inland rail project contract award

The Projects General Manager of ARTC Victoria and South Australia spoke about the project. Ed Walker began by acknowledging McConnell Dowell’s contract awarding. He further shed light on the company’s proven experience, especially in the delivery of major rail and infrastructure projects. The creative construction company has delivered railway stations, bridges as well as multi-million railroads in both New Zealand and Australia.

Moreover, the Victoria inland rail projects general manager said that the project marks a crucial step for Australia’s largest infrastructure development work. Furthermore, Ed Walker noted that the project is adhering to all the primary planning as well as environmental approvals.

Set to begin towards the end of the year, the project serves to bring a new wave of enthusiasm to North East Victoria.

Victoria Inland Rail project

Project Fact Sheet

Project: Beveridge to Albury section of Inland Rail

Location: Victoria, Australia

Corridor: Beveridge to Albury-Wodonga

Rail length: 262km

Project purpose: Upgrade infrastructure for double-stacked freight trains

Original contract value: Approximately A$200 million

Original contractor: McConnell Dowell

Tranche 1:

Status: Complete

Sites: Wangaratta, Glenrowan, Barnawartha North and Seymour

Tranche 2:

Status: Under construction

Contractor: John Holland

Sites: Eight locations between Benalla and Wandong

Remaining clearance site: Tallarook

Wider program: Inland Rail

Target wider completion: Beveridge to Parkes by the end of 2027

Project Team

Owner: Australian Government

Rail infrastructure manager: Australian Rail Track Corporation

Inland Rail delivery organization: Inland Rail

Tranche 1 construction partner: McConnell Dowell

Tranche 2 construction partner: John Holland

Original Tranche 1 works: Wangaratta, Glenrowan, Barnawartha North and Seymour

Current Tranche 2 works: Benalla, Euroa, Seymour, Tallarook, Broadford and Wandong

Wider rail program: Inland Rail

Future freight connection: Beveridge to Parkes corridor

Source: constructionreviewonline.com All rights reserved. Unauthorized reproduction prohibited.

Company profiles

Comments

Leave a Reply

Your email address will not be published. Required fields are marked *