COOEC has inked an $800m subsea pipeline contract for the Maydan Mahzam offshore oil field in Qatar with QatarEnergy. The package, EPIC2-MM Subsea Pipeline, Power Cables & Umbilicals, is part of QatarEnergy’s redevelopment of the Maydan Mahzam offshore oil field. In addition, Offshore Oil Engineering Co. announced in a Nov. 21 filing with the Shanghai Stock Exchange that it had signed. Furthermore, the contract is valid for 66 months, or approximately QAR 2.9 billion in value.
The deal extends a deep Qatar relationship for the Chinese contractor. COOEC is a subsidiary of CNOOC. Moreover, the company described the award as a testament to the company’s good client recognition in Qatar. It also set the contract as a basis for its foreign policy in the framework of China’s 15th Five-Year Plan.
Other Projects
Kuwait has placed the $3.3 billion Al-Zour Dorra onshore gas plant in bid evaluation. Four international contractors are now in contention for the facility. Furthermore, the plant sits next to the Al-Zour refinery, and state-owned Kuwait Gulf Oil Company owns the development. The bid deadline remains at Dec. 29 in the meantime. The plant is the cornerstone of Kuwait’s efforts to develop the Dorra field. Its design processes 632 million cubic feet a day of gas and 60,000 barrels a day of condensate. Furthermore, the feed comes from the Dorra field in the Saudi-Kuwaiti Divided Zone. Technip Energies finished the front-end engineering and design for the project, according to the report.
Scope of the Maydan Mahzam Subsea Pipeline Contract
The EPIC package includes engineering, procurement, construction, installation and pre-commissioning. In addition, the primary work involves laying over 100 km of subsea pipelines, power cables and umbilicals offshore Qatar. Oil, gas and water will be transported between platforms via subsea pipelines. Meanwhile, power cables are used to provide power to the offshore facilities. Umbilicals then bundle power, control signals and chemicals to subsea equipment.
COOEC’s role covers the entire delivery chain. The company is responsible for project management, detailed design, procurement, construction, transport, installation and pre-commissioning. Furthermore, it will lay down related facilities in parallel with the main lines. Payments are made monthly, according to the actual construction progress. As a result, cash is not deposited in milestones, but rather in verified work over the 66-month period.
Outlook for the COOEC Qatar workload
The award is COOEC’s third significant QatarEnergy project in the past two years, according to Saudi Gulf Projects. The company secured the subsea pipelines and cables EPC package valued at approximately $900 million for the Al-Shaheen field’s Project Ru’ya in 2024. Moreover, it initiated the $4 billion Bul Hanine EPIC project in October 2025. Furthermore, the contract is the biggest international offshore oil and gas EPC contract that a Chinese company has secured. In September 2026, construction began on Bul Hanine at COOEC’s yard in Qingdao.
The broader Qatar programme is conducted on multiple tracks. COOEC also partners with Saipem on the $4 billion COMP5 package of the North Field Production Sustainability project for QatarEnergy LNG. Furthermore, QatarEnergy is redeveloping Bul Hanine and Maydan Mahzam as a joint project to prolong the life of the old offshore fields. Fugro has been involved in seabed survey and geo-consultancy services for both. Maydan Mahzam is located in Qatar’s first large-scale offshore decommissioning project, where McDermott was awarded the definition engineering contract. In the end, the timeline is from Nov. 21 filing to a 66-month delivery window, and the Bul Hanine buildout is underway with it.

Project Overview
- Contract Value: About $800 million
- QAR Equivalent: About 2.9 billion
- Client: QatarEnergy
- Contractor: COOEC, CNOOC subsidiary
- Field: Maydan Mahzam, offshore Qatar
Scope
- More than 100 km subsea pipelines
- Power cables supply offshore facilities
- Umbilicals carry power and chemicals
- Associated facilities installation included
Project Highlights
- Third major QatarEnergy award in two years
- EPIC covers pre-commissioning too
- Monthly payments track progress
- Builds on $900 million Ru’ya win
Key Developments
- Filing disclosed signing Nov. 21
- Contract spans 66 months
- Bul Hanine construction started September
- COMP5 partnership continues with Saipem
Key Challenges
- 66-month offshore execution window
- Ageing field redevelopment demands
- Parallel decommissioning programme ahead
- Multi-package coordination with Saipem
Outlook
- Delivery runs 66 months
- Bul Hanine buildout advances
- Fields redevelopment extends life
- Qatar pipeline backlog grows