Al Ajban Abu Dhabi Solar Project Reaches Key Milestones

Home » Energy » Al Ajban Abu Dhabi Solar Project Reaches Key Milestones

Project Fact Sheet

Project NameAl Ajban Solar PV Independent Power Project

LocationAbu Dhabi, UAE

Capacity1.5 GW

Project TypeUtility-scale solar PV

Contract TypeEPC

Construction StartNovember 2024

Main MilestoneFirst panel installation February 2026

Expected Commercial OperationsQ3 2026

Project Value$748 million

StatusUnder construction

Project Team

Developer / ClientMasdar

Offtaker / Energy AuthorityEmirates Water and Electricity Company

EPC ContractorPower Construction Corporation of China

Consortium / Project Partners:

  • EDF Renewables
  • Korea Western Power

Technology / SuppliersArctech – solar tracker supplier

Source: constructionreviewonline.com All rights reserved. Unauthorized reproduction prohibited.