Egypt’s Gulf of Suez Wind Farm II: A Major Milestone in Africa’s Renewable Energy Expansion

Home » Energy » Wind power » Egypt’s Gulf of Suez Wind Farm II: A Major Milestone in Africa’s Renewable Energy Expansion

Egypt’s Gulf of Suez wind farm corridor is continuing to expand, with new grid infrastructure being developed to accommodate additional renewable electricity from the region. On October 25, 2026, the Egyptian Electricity Transmission Company (EETC) signed a contract with Wadi El Nile Contracting and Real Estate Investments for a 66-kilometre, 500-kilovolt double-circuit overhead transmission line extending towards the Sixth of October transformer substation.

The project, scheduled for completion within 12 months, is intended to transmit electricity generated by Gulf of Suez wind projects. The 66-kilometer transmission line will also strengthen the national grid’s capacity to integrate renewable power.

EETC’s latest transmission line contract follows the commissioning of the 650 MW Gulf of Suez Wind Farm II in June 2025. It emphasizes the importance of transmission infrastructure in supporting Egypt’s growing wind energy capacity. This also comes as Egypt’s Cabinet approves golden licenses for two 900 MW wind farms in the Red Sea and Gulf of Suez regions.

Egypt’s Gulf of Suez Wind Farm II: A Major Milestone in Africa’s Renewable Energy Expansion

All You Need to Know About Egypt’s Gulf of Suez Wind Farm II, Africa’s Largest Wind Power Plant

Reported October 1, 2025 – The Gulf of Suez Wind Farm II with a capacity of 650 MW is Africa’s largest wind power plant built in the Arab Republic of Egypt. The wind farm was completed and kicked off commercial operation on June 30, 2025.

The wind power plant is located in the Gulf of El Zayt along the Gulf of Suez. Furthermore, the Gulf of Suez Wind Farm II has a total of 84 wind turbines each with a capacity of 6.0 MW each and 20 wind turbines with a capacity of 7.5 MW each. Additionally, the latter are the largest-class onshore wind turbines in the world.

Gulf of Suez Wind Farm II in Egypt commenced commercial operations and was commissioned on June 30, 2025. The project is a gigantic project with a total capacity of 650 MW. Moreover, it is the largest functional wind power facility in Africa and the Middle East. The project, which is owned by Red Sea Wind Energy (consortium of Eurus Energy, Toyota Tsusho, Engie, and Orascom Construction), was commissioned ahead of schedule.

Apart from the Suez II Wind Farm, Egypt has a vibrant pipeline of renewable energy projects coming up. Some of these include Infinity Power’s solar-battery project. The project is expected to produce 1,200 MW once complete and is is estimated will cost $1 billion. Another notable one is the Infinity Power’s 200 MW Wind Project in Ras Ghareb that is set to commence construction in September 2025.

Also read: Siemens Gamesa Signs Agreement for Establishing 500MW Gulf of Suez Wind Power Project

Gulf of Suez Wind Farm II
The wind farm with a capacity of 650 MW is Africa’s largest wind power plant built in the Arab Republic of Egypt.

Project Factsheet

Project name: Gulf of Suez Wind Farm II. Also, it is referred to as Gulf of Suez 2 Wind Farm or Red Sea Wind Energy.

Location: Gulf of Suez, near Ras Ghareb, Red Sea Governorate, Egypt.

Capacity: 650MW

Number of turbines: The 650 MW project is comprises of 104 wind turbines. 84 for the initial 500 MW and 20 for the 150 MW extension.

Cost: $790 million

Developers: Toyota Tsusho Corporation, Eurus Energy Holdings Corporation, ENGIE, and Orascom Construction

Also read: Africa’s largest solar photovoltaic farm Obelisk solar project in Egypt to receive US$184m

Operator of the Gulf of Suez Wind Farm II

The sole operator of Gulf of Suez Wind Farm II is Red Sea Wind Energy S.A.E. This is a local operating company that has investments from Eurus Energy, Toyota Tsusho and France-based independent power producer Engie S.A. Egyptian construction company Orascom Construction PLC is also invested in the company.

Also read: Why Battery Storage is Becoming Essential for Solar and Wind Projects

Significance of the Project

The generated electricity from the wind power plant will be supplied to the Egyptian Electricity Transmission Company under a 25-year power purchase agreement. Additionally, the wind project will provide electricity that is equivalent to the power consumption of approximately 1,100,000 Egyptian households. Also, it is expected to cut CO2 emissions by approximately 1,450,000 tons annually.

Also read: AMEA Power Commissions Amunet Wind Power Plant Project in Egypt, Africa’s Largest Wind Power Plant

Source: constructionreviewonline.com All rights reserved. Unauthorized reproduction prohibited.