Hombre Muerto West Phase 1 Moves Into Production

Home » Mining » Hombre Muerto West Phase 1 Moves Into Production

The Hombre Muerto West Phase 1 Project is a lithium brine operation located in Catamarca Province, Argentina, and it has now moved from construction into production. Galan Lithium reported in September that its nanofiltration plant is performing in line with piloting results, with first lithium chloride concentrate sales on track for the fourth quarter of 2026.

Hombre Muerto West Phase 1 Schedule and Expansion

That timeline sits well behind the mid 2025 start Galan once targeted, and the initial 4,000 metric ton a year rate is now expected in the first half of 2027. Earthworks to lift output to 5,200 metric tons have started. Similar cost and schedule pressures shaped Freeport’s $4.5 billion Bagdad copper expansion in Arizona.

Project Overview

  • Project Name: Hombre Muerto West (HMW) Phase 1
  • Location: Catamarca Province, Argentina
  • Owner: Galan Lithium Limited (100 percent)
  • Product: Lithium chloride concentrate, with Galan targeting about 6 percent lithium content
  • Project Value: Not publicly disclosed
  • Key Components: Evaporation ponds and a nanofiltration plant for impurity removal
  • Initial Capacity: 4,000 metric tons a year of lithium carbonate equivalent, expected in the first half of 2027
  • Phase 1 Expansion: Earthworks under way to reach 5,200 metric tons a year, with higher volumes expected in the second half of 2027
  • First Sales: Lithium chloride concentrate sales targeted for the fourth quarter of 2026
  • Future Phases: A Phase 2 mining permit allows up to 21,000 metric tons a year, subject to project financing

Project Team

  • Owner and Developer: Galan Lithium Limited
  • Nanofiltration Plant Capacity Upgrade: Authium
  • Strategic Investor: Chemphys
Hombre Muerto West Phase 1 Moves Into Production
Hombre Muerto West Phase 1 Moves Into Production

Reported 6th December 2023: Updates on the progress of work on the Hombre Muerto West Phase1 lithium brine project were recently provided by Galan Lithium Limited. The company is hoping to see the project, which it fully owns, deliver lithium chloride production in H1, by 2025.

With an impressive 65% completion rate, it is said that construction of pond one is currently on track. Furthermore, already on track, liners as well as their installation is expected to commence late December of this year.

Also read: Zimbabwe’s Arcardia Lithium Project to promote employment

Coinciding with the start of the process of evaporation over the summer, pond 1 filling is expected in the first quarter of 2024. Ponds 2 and 3 preparations, which involve the removal of topsoil, are in progress.

Also in good progress is the new camp’s development and the infrastructure. Additionally, the last modules are considerably in place too. Marking a huge milestone in the lithium brine project’s advancement, the technical due diligence of Glencore recently started officially. 

The HMW project was split into four phases of production according to the previously made announcement. As governed by the ratified permits regarding production, Hombre Muerto West Phase 1 DFS focused on 5.4ktpa LCE of a lithium chloride concentrate production by June 2025.

The second phase of the project is aimed at a 2026 production of 21 ktpa LCE of a lithium chloride concentrate. It will be closely followed by the third phase which involves the production of 40 ktpa LCE. This is slated to be delivered by 2028. A 60 ktpa LCE is the target for phase four of the project. This is also expected to be ready by 2030.

Lithium brine obtained from HMW as well as other projects that are fully owned by Galan in Argentina, will be included in phase four. 

When can we expect first production from the ongoing Hombre Muerto West Phase 1 project?

According to Juan Pablo (JP) Vargas de la Vega, Galan’s Managing Director, they are confident on the establishment of Phase 1 HMW. The company hope to see its first production in the summer of 2025. He confirmed that construction works on pond 1 are in good progress and in line with what they expected. 

A cohesive and a highly competent team has been assembled by Galan with the required expertise to construct the ponds. The team will also build the infrastructure needed to deliver the HMW project’s first production successfully.

The project’s authorization

In August 2023, construction permits to carry out the Hombre Muerto West Phase1 Project were granted to Galan Lithium Limited by the Argentine Mines Department Minister. The permit included the construction of ponds, an onsite laboratory, and a carbonate plant. Also in the permit was a camp as well as the necessary infrastructure needed for the project’s execution.

Source: constructionreviewonline.com All rights reserved. Unauthorized reproduction prohibited.

Featured Companies

Comments

Leave a Reply

Your email address will not be published. Required fields are marked *