Project Cannoli: Construction Halted at $2bn Google Data Center in Van Buren Township, Michigan

Home » Buildings » Data Center » Project Cannoli: Construction Halted at $2bn Google Data Center in Van Buren Township, Michigan
Project Cannoli

Project Cannoli construction in Van Buren Township, Michigan, has stopped following a Wayne County enforcement order. The county cited missing construction permits and unauthorized activities affecting local drainage infrastructure. The stoppage interrupts early development of a hyperscale data center valued at more than $2 billion.

The 282-acre campus will serve Google’s expanding computing infrastructure requirements. However, the latest enforcement action raises questions about construction compliance and stormwater management. The developer must resolve the outstanding county requirements before resuming work.

Project Cannoli Construction Halted Over County Permit Violations

Wayne County issued a stop-work order on November 20, 2026, to the project developer. The order identified PDC AK LPIV, LLC, associated with Panattoni Development Company. County officials cited unauthorized construction activities affecting several county drains across the development site.

Wayne County Director of Public Services Oladayo Akinyemi signed the enforcement order. He identified construction within drainage easements and obstructions affecting existing drainage channels. According to the county, these activities create significant flooding risks.

Additionally, the county identified construction within its road right-of-way. Officials said this activity violated Wayne County’s Stormwater Control ordinance. The developer must obtain the required county construction permit before restarting work.

Furthermore, the developer must reach agreements with the county drain commissioner or relevant local drainage districts. These agreements must address construction activities affecting stormwater runoff.

County spokesperson Matt Allen confirmed the construction suspension to Michigan Public on November 24. He indicated that construction had stopped following the enforcement notice.

Meanwhile, Panattoni acknowledged the county’s concerns and committed to addressing them. The developer said its team was working directly with county officials. It also pledged to review the identified issues and clarify outstanding requirements.

Project Cannoli Construction and the 282-Acre Data Centre Development

The development occupies approximately 282 acres near Haggerty Road in Van Buren Township. The site lies between Interstate 94 and Interstate 275, west of Detroit Metropolitan Airport.

Panattoni is developing the campus for Google, which will operate the completed facility. The development includes multiple buildings supporting large-scale computing and network infrastructure.

Township planning documents identify three data processing buildings within the development. These buildings will range between approximately 87,000 and 300,000 square feet. The wider campus also includes administrative and network service facilities.

The project received preliminary site plan approval in February 2026. Subsequently, the Van Buren Township Planning Commission approved its final site plan on October 14. The commission voted 5–1 in favor of the development.

However, township approval did not replace separate county construction requirements. This distinction now forms the center of the enforcement dispute.

Wayne County commissioners also approved the project’s tax incentives and community benefits arrangements. They overrode County Executive Warren Evans’ veto on October 1. The commission clarified that its decision concerned tax benefits, not construction authorization.

Michigan’s data centre expansion also extends beyond the Detroit metropolitan area. Microsoft has confirmed plans for a new data centre in Grand Rapids, following its acquisition of 316 acres in Gaines Township for $45.3 million. The proposed development adds to the state’s growing pipeline of hyperscale computing infrastructure, although its construction timeline remains unconfirmed. The Microsoft data centre development in Grand Rapids, Michigan highlights the increasing competition for infrastructure, electricity and suitable development sites across the state.

Project Cannoli Construction Faces Infrastructure and Energy Challenges

Beyond the permitting dispute, the development presents substantial infrastructure requirements. The completed facility could require approximately one gigawatt of electricity. Its projected daily water consumption ranges between two million and 3.6 million gallons.

In March 2026, Google announced an agreement with DTE Energy. The arrangement involves funding 2.7 gigawatts of electricity generation and capacity. It includes investments in renewable energy and battery storage infrastructure.

However, Michigan Attorney General Dana Nessel challenged the electricity agreement. Her filing argued that the arrangement could transfer infrastructure costs to ordinary electricity customers.

The project also carries significant economic commitments for the surrounding community. Wayne County identifies the development as a private infrastructure investment exceeding $2 billion.

Furthermore, the developer’s commitments include $15 million for Wayne County over 12 years. Another $15 million commitment will support Van Buren Township during the same period.

The township also approved approximately $125 million in tax incentives. Meanwhile, the county expects the development to generate thousands of union construction jobs.

Consequently, resolving the county’s drainage and permitting concerns remains essential. The construction suspension introduces another regulatory hurdle for the major infrastructure investment. Neither the county nor the developer has announced a confirmed restart date.

Project Cannoli Michigan

Source: constructionreviewonline.com All rights reserved. Unauthorized reproduction prohibited.