Google Commits $9B to Virginia Expansion: Massive New AI Data Center Campus Announced

Home » Buildings » Data Center » Google Commits $9B to Virginia Expansion: Massive New AI Data Center Campus Announced
Google’s Data Center in India

Project Overview

InvestorGoogle Inc.

Total Investment$9 billion

LocationMulti-site expansion across Virginia

Primary SiteMeadowville Technology Park, Chesterfield County

Additional SitesTwo campuses in Loudoun County, one in Prince William County

Chesterfield County Campus Details

SiteSize: 300 acres along Bermuda Hundred Road

Initial PhaseSingle building

Construction Timeline18-24 months (typical for hyperscale facilities)

Tax AgreementCounty to refund difference if server tax rate exceeds current 24¢ per $100

InfrastructureGoogle to cover excess water infrastructure costs beyond agreed levels

Energy and Technical Specifications

Power SourceDominion Energy regional grid

Nearby InfrastructureNew Meadowville substation supporting 300+ MW

Efficiency TargetGoogle’s global average PUE of 1.12 (industry-leading)

Cooling TechnologyHigh-efficiency systems, likely including direct liquid cooling

Power DensityExpected to support up to 80 kW per rack

Source: constructionreviewonline.com All rights reserved. Unauthorized reproduction prohibited.

Featured Companies

Comments

Leave a Reply

Your email address will not be published. Required fields are marked *