Israeli construction and infrastructure company Shikun & Binui announced on Monday that it has been awarded a $1.29 billion contract, alongside an American partner, to replace an aging bridge spanning the Susquehanna River in Pennsylvania. The bridge replacement project, valued at more than 4 billion shekels, will link Harrisburg and Lemoyne, with Shikun & Binui holding an 80% stake worth approximately 3.26 billion shekels. Construction works at the bridge are expected to commence in 2027 and continue through 2039.
The Susquehanna River stretches approximately 710 kilometers (441 miles). It passes through New York, Pennsylvania and Maryland before emptying into the Chesapeake Bay. Furthermore, it is the longest river on the eastern U.S. seaboard. The bridge replacement is part of a broader transportation infrastructure project commissioned by the Pennsylvania Department of Transportation. Also, it shows the institutions commitment to ensuring Pennsylvania has good transport infrastructure in bid to enhance connectivity and integration.
Shikun & Binui Submits Lowest Bid
Shikun & Binui submitted the lowest bid among the competing contractors. The company offered to complete the bridge replacement and related transportation infrastructure work for $1.289 billion. Additionally, the company said the contract covers construction rather than design. This means that it will not bear responsibility for the project’s engineering design risks. Despite securing the work with the lowest bid, management expects the gross profit margin to remain in line with the rates it typically targets for comparable projects.

Shikun & Binui CEO Amit Birman said the project would be carried out through the group’s American subsidiary and would require a carefully phased construction process to maintain traffic throughout the replacement. “This is a complex project that will be carried out in stages to keep traffic moving across the bridge,” he said.
Other Contracts By Shikun & Binui in the US
Birman noted that the company already has substantial experience in American bridge construction, including a $600 million bridge replacement project in Washington with partners and another major project involving five bridges in Pennsylvania. Unlike the latest contract, however, those Pennsylvania bridges are land crossings rather than structures spanning a river.
Shikun & Binui to Partner with Pennsylvania-Based New Enterprise on the Project
Lastly, the Israeli company will work with Pennsylvania-based New Enterprise, which will hold the remaining 20% of the venture. Birman said the partnership offers an important cost advantage. This is because the American company operates concrete and asphalt production facilities and quarries, giving the consortium access to construction materials at competitive prices. “That allows us to offer a lower price than our competitors,” he explained, emphasizing that Shikun & Binui will serve as the construction contractor while the Pennsylvania Department of Transportation was responsible for the design.
I-83 South Bridge Replacement Project Factsheet
Project Name: I-83 John Harris Memorial (South) Bridge Replacement
Location: Spanning the Susquehanna River between Harrisburg (Dauphin County) and Lemoyne (Cumberland County), Pennsylvania
Client: Pennsylvania Department of Transportation (PennDOT)
Contract Value: $1.289 billion (over 4 billion NIS)
Contractors & Stakes:
Shikun & Binui (via U.S. subsidiary): 80% stake (3.26 billion NIS)
New Enterprise Stone & Lime Co.: 20% stake (providing local concrete, asphalt, and quarry materials)
Project Scope: Full replacement of the aging 1960 bridge (which carries over 125,000 vehicles daily), plus surrounding interchange reconfigurations, viaduct reconstruction, and local bridge replacements.
Contract Model: Construction-only (PennDOT retains engineering design responsibility and risk)
Timeline: 2027 – 2039 (built in stages to keep river traffic open throughout construction)