The Jeddah Tower halfway mark is close. The tower in Saudi Arabia, set to become the world’s first 1,000-meter building, has passed 120 floors. Its project team expects to reach the 500-meter halfway point around Thanksgiving. The Jeddah Tower is approaching the halfway point of its climb past 1,000 meters.
Where the Jeddah Tower halfway mark stands
Kingdom Holding reported on November 2 that the tower had reached 120 floors, at about 482 meters. The project team later said it had reached the 121st floor at about 484 metres. The halfway point is the 125th floor, at about 500 meters, so only a few floors remain. The tower is already breaking records. It has passed the Petronas Towers’ 452 metres and, according to the team, the world’s tallest all-residential tower, New York’s Central Park Tower, at just over 1,550 feet. Once finished, it will stand more than 1,000 metres tall, well above the 828-metre Burj Khalifa.
How the team is building a kilometre-high tower
The pace is fast. Crews are completing about one floor a week with a workforce of around 5,200. In addition, they have poured more than 322,000 cubic metres of concrete and installed more than 3,900 façade panels.
The design helps. The three-legged structure tapers as it rises, which gives it stability and helps it manage wind forces. Adrian Smith + Gordon Gill Architecture designed the tower, and Saudi Binladin Group is building it for the Jeddah Economic Company. The tower will anchor the first phase of Jeddah Economic City.
The climb has been a long one. Construction stopped in 2018 and resumed years later, so the current pace marks a big change

Other projects
Tahrir petrochemicals complex Egypt remains one of the country’s most ambitious industrial developments as Carbon Holdings continues advancing the estimated $11 billion project in Ain Sokhna. Moreover, the complex targets large-scale petrochemical production to support exports and local industries. However, recent updates indicate slower-than-expected construction progress despite strong early momentum.
What comes after the halfway mark
Three major steps remain. First comes the Sky Terrace at about 630 metres, which is designed to be the world’s highest outdoor observation deck. Then comes the sky raft, a concrete slab that marks the start of the tower’s pure spire section. Finally, the team will build the spire itself.
Challenges remain. The team has flagged weather risks, including extreme heat in Jeddah’s summer and the possibility of a strong El Niño. Even so, the project director says progress is on track for the 2028 completion date, and Time Out reports completion in late 2028.
The race for height is heating up elsewhere too. In Dubai, Burj Binghatti Jacob & Co. Residences is targeting one floor a week as it rises toward the title of the world’s tallest residential building.
Fact Sheet
Project: Jeddah Tower (Jeddah Economic Company Tower)
Location: Jeddah Economic City, Saudi Arabia
Developer: Jeddah Economic Company
Architect: Adrian Smith + Gordon Gill Architecture
Contractor: Saudi Binladin Group
Progress: 120+ floors, about 482 to 486 meters (early November 2026)
Halfway mark: 125th floor, about 500 meters
Planned height: more than 1,000 meters
Planned floors: about 157
Sky terrace: about 630 meters
Completion target: late 2028