Project Fact Sheet
Project NameKOREplex Battery Manufacturing Plant (Arizona Gigafactory)
Value$1.2 billion (original estimate)
LocationBuckeye, Arizona, United States
Project TypeLithium-ion battery cell manufacturing facility
Land Area~200 acres (planned full buildout)
Building SizeOver 2 million sq ft planned at full expansion
TechnologyLithium-ion (NMC and LFP chemistries)
Original Capacity TargetUp to 12 GWh annual battery cell production
Status (2026)Delayed / restructuring phase / limited advancement
Construction StageEarly site works completed; major construction paused
Contractor (early phase)Yates Construction
Engineering PartnerSSOE Group
Key ObjectiveDomestic US battery supply chain development
Project Team
KORE Power— Project developer and technology owner
Yates Construction— Early-stage general contractor and construction planning lead
SSOE Group— Engineering, procurement and site design services
City of Buckeye Planning Authorities— Local permitting and zoning approvals
Arizona Commerce Authority— Investment facilitation and industrial development support
US Department of Energy(historical financing engagement) — Potential loan and funding participation
Battery supply chain vendors— Equipment and cell manufacturing technology providers
Electrical utilities(Arizona Public Service) — Grid connection and substation integration planning
Also read400MWh Weld Energy Storage Project in Platte River, Colorado Advances as PRPA Finishes Key Steps