Project Fact Sheet
- Project name: Livingstone Solar Farm and Battery Energy Storage System (BESS)
- Project developer: Neoen
- Parent company: Brookfield Asset Management
- Location: Near Big Springs and Gregadoo, close to Wagga Wagga, New South Wales, Australia
- Site area: Approximately 2,900 hectares
- Solar generation capacity: 300-600MW
- Battery power capacity: Up to 400MW
- Battery storage capacity: Up to 1,600MWh
- Battery duration: Four hours at maximum rated output
- Existing transmission infrastructure: 330kV Wagga-Lower Tumut transmission line
- Proposed grid connection: Gugaa Substation
- Associated transmission project: HumeLink 500kV transmission project
- Environmental approval submission: November 2026
- Expected construction commencement: 2030
- Estimated construction period: 12-14 months
- Current status: Environmental assessment and project development
- Key feature: Proposed agrisolar integration allowing continued agricultural activities alongside solar generation.
Project Team
- Neoen – Project developer, owner and proposed operator.
- Brookfield Asset Management – Parent company and investment owner of Neoen.
- Transgrid – NSW transmission network operator responsible for the proposed Gugaa Substation and HumeLink transmission infrastructure.
- Australian Department of Climate Change, Energy, the Environment and Water – Federal environmental assessment and approval authority.
- NSW Government – State-level planning and development approval authority.